How many solar installs has MD Electric & Solar Inc. done in California, and which license number is on its installs?

MD Electric & Solar Inc. has 84 residential solar installs interconnected in California, active in the records from 2011 through 2025 (Mar 23, 2011 to Apr 22, 2025), most of them in Sonoma County (54), Mendocino County (29) and Shasta County (1). CSLB lists license 815891 (M D ELECTRIC & SOLAR INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, C-46, expires Aug 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
84
Last 24 months
4
Total capacity
431.8 kW DC
Median system size
4.7 kW DC
With battery storage
1.2% all time; 25.0% last 24 months
Third-party owned
0.0% of 84 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
2 installs, latest Apr 22, 2025
Ownership types recorded
none recorded
Median battery size
15.2 kWh (1 installs list a capacity)
First install
Mar 23, 2011
Latest install
Apr 22, 2025
Counties
3
Utilities
PGE 84
CSLB license
815891

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2011 to 2026

YearInstalls interconnectedWith battery storage
201150
2012120
201360
201450
201590
2016190
201780
2018100
201950
202000
202100
202210
202300
202431
202510
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

2 of its 84 interconnected installs (2.4% of the 84 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 0.0% of those include battery storage. The latest Net Billing Tariff install was approved Apr 22, 2025.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.05666.7%not counted
NEM 2.02631.0%1 (3.8%)
Net Billing Tariff22.4%0 (0.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on MD Electric & Solar Inc.’s installs. No residential system in the file lists a third-party owner name that matches MD Electric & Solar Inc. exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 4 of MD Electric & Solar Inc.’s 4 installs name a module maker in the “Generator Manufacturer” fields, and most of those (4, 100.0%) used modules recorded as REC.

In the last 24 months, 4 of MD Electric & Solar Inc.’s 4 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (3, 75.0%) used inverters recorded as Sol-Ark.

0 of 1 battery-paired PG&E and SCE installs (0.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerREC44
SimpliPhi Power, Inc.1not in top list
Inverter makerSol-Ark33
Enphase143

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 84 of 84 installs, inverters on 84. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names MD Electric & Solar Inc. as developer on 2 battery storage projects and as installer on 2 (2 name it as both), 2 projects in all with 43 kWh of storage. 2 have the status Paid, with $20,800 in current incentive allocations. Applications were received from Apr 15, 2024 to Oct 24, 2024.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid243$20,800

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency130$17,5001$17,500
Large-Scale Storage113$3,3001$3,300

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
815891M D ELECTRIC & SOLAR INC (Corporation)CLEARC-10 Electrical Contractor; C-46 Solar ContractorDec 16, 2002Aug 31, 202859

License numbers are the ones the utilities recorded on the interconnection applications (59 of 84 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 815891. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Sonoma54
Mendocino29
Shasta1

Top cities

CityInstalls
The Sea Ranch52
Gualala25
Point Arena4
Anderson1
Annapolis1
Sebastopol1

Names as recorded by the utilities

The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
MD Electric & Solar Inc.38
MD Electric & Solar Inc37
MD Electric & Solar4
MD ELECTRIC & SOLAR INC2
MD Electric and Solar2
MD Electric & Solar, Inc.1

Common questions

Where does MD Electric & Solar Inc. install solar?

Its installs are spread across 3 counties. The most are in Sonoma County (54 installs), followed by Mendocino County (29).

How often does MD Electric & Solar Inc. install batteries with solar?

1.2% of its interconnected solar installs include battery storage across all years, and 25.0% in the last 24 months (1 of 4).

How many MD Electric & Solar Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

2 of its 84 interconnected installs (2.4% of the 84 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 0.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.