Byldan Corporation
How many solar installs has Byldan Corporation done in California, and which license number is on its installs?
Byldan Corporation has 411 residential solar installs interconnected in California, active in the records from 2001 through 2017 (Nov 6, 2001 to May 7, 2017), most of them in Santa Cruz County (301), San Mateo County (41) and Fresno County (26). The utilities did not record a CSLB license number on enough of these installs to look one up.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 411
- Last 24 months
- 0
- Total capacity
- 666.3 kW DC
- Median system size
- 1.4 kW DC
- With battery storage
- 0.0% all time; no installs in the last 24 months last 24 months
- Third-party owned
- 0.0% of 411 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- none recorded
- First install
- Nov 6, 2001
- Latest install
- May 7, 2017
- Counties
- 6
- Utilities
- PGE 411
- CSLB license
- none reported
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2001 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2001 | 4 | 0 |
| 2002 | 1 | 0 |
| 2003 | 15 | 0 |
| 2004 | 158 | 0 |
| 2005 | 60 | 0 |
| 2006 | 58 | 0 |
| 2007 | 48 | 0 |
| 2008 | 28 | 0 |
| 2009 | 37 | 0 |
| 2010 | 1 | 0 |
| 2011 | 0 | 0 |
| 2012 | 0 | 0 |
| 2013 | 0 | 0 |
| 2014 | 0 | 0 |
| 2015 | 0 | 0 |
| 2016 | 0 | 0 |
| 2017 | 1 | 0 |
| 2018 | 0 | 0 |
| 2019 | 0 | 0 |
| 2020 | 0 | 0 |
| 2021 | 0 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 411 interconnected installs with a tariff recorded (411) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 410 | 99.8% | not counted |
| NEM 2.0 | 1 | 0.2% | 0 (0.0%) |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Byldan Corporation’s installs. No residential system in the file lists a third-party owner name that matches Byldan Corporation exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 376 of Byldan Corporation’s 411 installs name a module maker in the “Generator Manufacturer” fields, and most of those (201, 53.5%) used modules recorded as Sharp.
Across all years, 411 of Byldan Corporation’s 411 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (221, 53.8%) used inverters recorded as SMA.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Sharp | 0 | 201 |
| Astro Power, Inc | 0 | 104 | |
| Kyocera | 0 | 66 | |
| General Electric | 0 | 4 | |
| BP Solar | 0 | 1 | |
| Inverter maker | SMA | 0 | 221 |
| Sharp | 0 | 156 | |
| PV Powered | 0 | 26 | |
| Xantrex Technology Inc. | 0 | 5 | |
| Advanced Energy, Inc. | 0 | 2 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 376 of 411 installs, inverters on 411. See the methodology and the equipment index.
Contractor license
The utilities did not record a license number for enough of these installs to look one up.
License numbers are the ones the utilities recorded on the interconnection applications (1 of 411 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it.
Counties
| County | Installs |
|---|---|
| Santa Cruz | 301 |
| San Mateo | 41 |
| Fresno | 26 |
| Alameda | 18 |
| Santa Clara | 17 |
| Contra Costa | 8 |
Top cities
Names as recorded by the utilities
The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Byldan Corporation | 390 |
| Byldan Corp. | 14 |
| Byldan Corp | 4 |
| Byldan | 2 |
| BYLDAN CORPORATION | 1 |
Common questions
Where does Byldan Corporation install solar?
Its installs are spread across 6 counties. The most are in Santa Cruz County (301 installs), followed by San Mateo County (41).
How often does Byldan Corporation install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years.
How many Byldan Corporation installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 411 interconnected installs with a tariff recorded (411) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.