FLORES ELECTRIC

How many solar installs has FLORES ELECTRIC done in California, and which license number is on its installs?

FLORES ELECTRIC has 156 residential solar installs interconnected in California, active in the records from 2021 through 2026 (Feb 16, 2021 to Jul 27, 2026), most of them in San Bernardino County (156). CSLB lists license 638115 (sole owner license, name not shown) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires May 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
156
Last 24 months
65
Total capacity
609.1 kW DC
Median system size
3.2 kW DC
With battery storage
0.0% all time; 0.0% last 24 months
Third-party owned
0.0% of 156 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
98 installs, latest Jul 27, 2026
Ownership types recorded
none recorded
First install
Feb 16, 2021
Latest install
Jul 27, 2026
Counties
1
Utilities
SCE 156
CSLB license
638115

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2021 to 2026

YearInstalls interconnectedWith battery storage
202150
2022300
2023340
2024350
2025300
2026 (through Aug 31, 2026)220

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

98 of its 156 interconnected installs (62.8% of the 156 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 0.0% of those include battery storage. The latest Net Billing Tariff install was approved Jul 27, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.05837.2%0 (0.0%)
Net Billing Tariff9862.8%0 (0.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on FLORES ELECTRIC’s installs. No residential system in the file lists a third-party owner name that matches FLORES ELECTRIC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 65 of FLORES ELECTRIC’s 65 installs name a module maker in the “Generator Manufacturer” fields, and most of those (60, 92.3%) used modules recorded as Qcells.

In the last 24 months, 65 of FLORES ELECTRIC’s 65 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (65, 100.0%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells60130
LONGi44
Mission Solar114
Inverter makerEnphase65115

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 151 of 156 installs, inverters on 156. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
638115Sole owner license (name not shown)CLEARC-10 Electrical ContractorFeb 18, 1992May 31, 2027156

License numbers are the ones the utilities recorded on the interconnection applications (156 of 156 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 638115. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
San Bernardino156

Top cities

CityInstalls
Hesperia57
Apple Valley41
Oak Hills18
Victorville11
Helendale8
Phelan8
Barstow5
Pinon Hills5
Chino Hills1
San Bernardino1
Upland1

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
FLORES ELECTRIC156

Common questions

Where does FLORES ELECTRIC install solar?

Its installs are spread across 1 county. The most are in San Bernardino County (156 installs).

How often does FLORES ELECTRIC install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years, and 0.0% in the last 24 months (0 of 65).

How many FLORES ELECTRIC installs are under NEM 3.0 (the Net Billing Tariff)?

98 of its 156 interconnected installs (62.8% of the 156 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 0.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.