Line Side Solar
How many solar installs has Line Side Solar done in California, and which license number is on its installs?
Line Side Solar has 49 residential solar installs interconnected in California, active in the records from 2014 through 2021 (Feb 4, 2014 to Apr 27, 2021), most of them in San Diego County (49). CSLB lists license 992833 (DESIGN BUILD ELECTRIC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires May 31, 2028.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 49
- Last 24 months
- 0
- Total capacity
- 502.4 kW DC
- Median system size
- 9 kW DC
- With battery storage
- not recorded (SDG&E files batteries as separate projects, not on the solar record) all time; no installs in the last 24 months last 24 months
- Third-party owned
- 0.0% of 47 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- none recorded
- First install
- Feb 4, 2014
- Latest install
- Apr 27, 2021
- Counties
- 1
- Utilities
- SDGE 49
- CSLB license
- 992833
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2014 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2014 | 2 | 0 |
| 2015 | 7 | 0 |
| 2016 | 15 | 0 |
| 2017 | 8 | 0 |
| 2018 | 5 | 0 |
| 2019 | 4 | 0 |
| 2020 | 6 | 0 |
| 2021 | 2 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 49 interconnected installs with a tariff recorded (49) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 16 | 32.7% | not counted |
| NEM 2.0 | 33 | 67.3% | not recorded |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Line Side Solar’s installs. No residential system in the file lists a third-party owner name that matches Line Side Solar exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 49 of Line Side Solar’s 49 installs name a module maker in the “Generator Manufacturer” fields, and most of those (46, 93.9%) used modules recorded as LG.
Across all years, 49 of Line Side Solar’s 49 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (41, 83.7%) used inverters recorded as SolarEdge.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | LG | 0 | 46 |
| SolarWorld | 0 | 3 | |
| Inverter maker | SolarEdge | 0 | 41 |
| SMA | 0 | 4 | |
| Enphase | 0 | 3 | |
| Power-One | 0 | 1 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 49 of 49 installs, inverters on 49. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 992833 | DESIGN BUILD ELECTRIC (Corporation) | CLEAR | C-10 Electrical Contractor | May 12, 2014 | May 31, 2028 | 34 |
License numbers are the ones the utilities recorded on the interconnection applications (35 of 49 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 992833. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Local solar permits naming its license
Solar permits in city and county open data that list Line Side Solar’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2018 | 2019 | 2020 | Total |
|---|---|---|---|---|---|
| unincorporated San Diego County | 992833 | 3 | 2 | 5 | 10 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Counties
| County | Installs |
|---|---|
| San Diego | 49 |
Top cities
| City | Installs |
|---|---|
| El Cajon | 31 |
| La Mesa | 4 |
| Jamul | 3 |
| Poway | 3 |
| San Diego | 3 |
| Bonita | 1 |
| Chula Vista | 1 |
| Lakeside | 1 |
| San Marcos | 1 |
| Spring Valley | 1 |
Names as recorded by the utilities
The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Line Side Solar | 49 |
Common questions
Where does Line Side Solar install solar?
Its installs are spread across 1 county. The most are in San Diego County (49 installs).
How often does Line Side Solar install batteries with solar?
Battery storage is not recorded on its interconnected solar installs: SDG&E files a battery as its own project record, not on the solar record.
How many Line Side Solar installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 49 interconnected installs with a tariff recorded (49) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.