Cienaga Services, Inc.

How many solar installs has Cienaga Services, Inc. done in California, and which license number is on its installs?

Cienaga Services, Inc. has 81 residential solar installs interconnected in California, active in the records from 2004 through 2026 (Dec 4, 2004 to Feb 16, 2026), most of them in San Luis Obispo County (73), Santa Barbara County (6) and Fresno County (1). CSLB lists license 512482 (CIENAGA SERVICES INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, C-20, C-36, C-46, expires Jul 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
81
Last 24 months
9
Total capacity
521.9 kW DC
Median system size
5.3 kW DC
With battery storage
6.2% all time; 22.2% last 24 months
Third-party owned
0.0% of 81 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
8 installs, latest Feb 16, 2026
Ownership types recorded
none recorded
Median battery size
19.6 kWh (5 installs list a capacity)
First install
Dec 4, 2004
Latest install
Feb 16, 2026
Counties
4
Utilities
PGE 80, SCE 1
CSLB license
512482

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2004 to 2026

YearInstalls interconnectedWith battery storage
200410
200510
200620
200720
200820
200930
201000
201110
201210
201330
201410
201500
201600
201700
201800
201910
202060
2021120
2022181
202381
2024141
202531
2026 (through Aug 31, 2026)21

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

8 of its 81 interconnected installs (9.9% of the 81 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 37.5% of those include battery storage. The latest Net Billing Tariff install was approved Feb 16, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.01721.0%not counted
NEM 2.05669.1%2 (3.6%)
Net Billing Tariff89.9%3 (37.5%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Cienaga Services, Inc.’s installs. No residential system in the file lists a third-party owner name that matches Cienaga Services, Inc. exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 9 of Cienaga Services, Inc.’s 9 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (3, 33.3%) used modules recorded as Canadian Solar.

In the last 24 months, 9 of Cienaga Services, Inc.’s 9 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (9, 100.0%) used inverters recorded as SolarEdge.

In the last 24 months, 2 of Cienaga Services, Inc.’s 9 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (2, 100.0%) used batteries recorded as SolarEdge.

4 of 5 battery-paired PG&E and SCE installs (80.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCanadian Solar337
SOLAREVER TECNOLOGIA DE AMERICA SA DE CV36
Axitec28
Mitrex1not in top list
Inverter makerSolarEdge955
Battery makerSolarEdge22

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 81 of 81 installs, inverters on 81. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
512482CIENAGA SERVICES INC (Corporation)CLEARC-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-36; C-46 Solar ContractorJun 16, 1987Jul 31, 202764

License numbers are the ones the utilities recorded on the interconnection applications (64 of 81 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 512482. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
San Luis Obispo73
Santa Barbara6
Fresno1
Tulare1

Top cities

CityInstalls
Arroyo Grande37
Nipomo18
San Luis Obispo9
Pismo Beach3
Santa Maria3
Avila Beach2
Orcutt2
Atascadero1
Grover Beach1
Kingsburg1
Paso Robles1
Santa Margarita1
Santa Ynez1
Visalia1

Names as recorded by the utilities

The utilities recorded this installer under 7 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
CIENAGA SERVICES INC63
Cienaga Services, Inc.9
Cienaga Services Inc.3
Cienaga Services,Inc.3
Cienaga Services1
Cienaga Services Inc1
Cienaga Services, Inc1

Common questions

Where does Cienaga Services, Inc. install solar?

Its installs are spread across 4 counties. The most are in San Luis Obispo County (73 installs), followed by Santa Barbara County (6).

How often does Cienaga Services, Inc. install batteries with solar?

6.2% of its interconnected solar installs include battery storage across all years, and 22.2% in the last 24 months (2 of 9).

How many Cienaga Services, Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

8 of its 81 interconnected installs (9.9% of the 81 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 37.5% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.