Solar installers in Visalia, California
Most installs here are in Tulare County.
Who installs the most solar in Visalia?
Ranked by interconnected installs in the last 24 months (Sep 2024 through Aug 2026), the top three installers in Visalia are Sunrun (1,054), Citadel Roofing and Solar (308) and LIFESTYLE SOLAR INC (221). They account for 1,583 of the 3,044 residential solar installs interconnected there in that window.
In all, 18,060 homes in Visalia have residential solar interconnected by PG&E, SCE or SDG&E through Aug 31, 2026. These are counts of connected systems, not a rating of any installer.
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installers ranked by interconnected installs, last 24 months
Sep 2024 through Aug 2026. Top 25 of 157 installers with installs in this window. 46 installs in the window were self-installed or had no installer recorded.
| 1 | Sunrun | 1,054 | 3,267 |
| 2 | Citadel Roofing and Solar | 308 | 324 |
| 3 | LIFESTYLE SOLAR INC | 221 | 712 |
| 4 | BRATTON SOLAR INC | 148 | 154 |
| 5 | FREEDOM FOREVER LLC | 110 | 491 |
| 6 | BRIGHT OPS | 99 | 127 |
| 7 | LIFESTYLE SOLAR ELECTRIC | 99 | 103 |
| 8 | SOLAR NEGOTIATORS | 91 | 285 |
| 9 | Tesla Energy Operations (formerly SolarCity) | 68 | 1,761 |
| 10 | GAF Energy | 56 | 56 |
| 11 | GRID Alternatives | 41 | 342 |
| 12 | Empower Electric Solar | 34 | 217 |
| 13 | SunPower | 30 | 930 |
| 14 | FREEDOM FOREVER NORTHERN CALIFORNIA LLC | 23 | 23 |
| 15 | JP ELECTRICAL SOLAR INC | 23 | 402 |
| 16 | FREEDOM FOREVER SOUTHERN CALIFORNIA LLC | 20 | 20 |
| 17 | Ilum Solar | 20 | 25 |
| 18 | DEMAND CONSTRUCTION | 18 | 27 |
| 19 | DISCOUNT CONSTRUCTION & ENGINEERING | 18 | 19 |
| 20 | EXO Energy | 17 | 41 |
| 21 | ALTSYS SOLAR INC | 14 | 100 |
| 22 | BRYTON POWER LLC | 14 | 15 |
| 23 | Air Sun Inc | 13 | 222 |
| 24 | ENERGY SERVICE PARTNERS INC DBA ESP CONTRACTING | 13 | 146 |
| 25 | K S OVERLAND CONTRACTING INC | 13 | 13 |
Most installs, all time
| 1 | Sunrun | 3,267 | 3,267 |
| 2 | Tesla Energy Operations (formerly SolarCity) | 1,761 | 1,761 |
| 3 | Vivint Solar Developer, LLC | 1,559 | 1,559 |
| 4 | SunPower | 930 | 930 |
| 5 | LIFESTYLE SOLAR INC | 712 | 712 |
| 6 | FREEDOM FOREVER LLC | 491 | 491 |
| 7 | JP ELECTRICAL SOLAR INC | 402 | 402 |
| 8 | SunStreet Energy Group LLC | 368 | 368 |
| 9 | GRID Alternatives | 342 | 342 |
| 10 | Citadel Roofing and Solar | 324 | 324 |
Installs by year
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2022 | 2,856 | 110 |
| 2023 | 2,437 | 195 |
| 2024 | 1,554 | 1,029 |
| 2025 | 1,603 | 1,301 |
| 2026 (through Aug 31, 2026) | 952 | 650 |
Under the Net Billing Tariff (NEM 3.0)
3,934 of the 18,060 residential solar installs in Visalia (21.8% of the 18,060 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 76.5% of those include battery storage. The latest was approved Aug 31, 2026. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023, under CPUC Decision D.22-12-056.
Installers ranked by Net Billing Tariff installs in Visalia
| 1 | Sunrun | 1,455 | 1,413 | 97.1% |
| 2 | Citadel Roofing and Solar | 321 | 202 | 62.9% |
| 3 | LIFESTYLE SOLAR INC | 238 | 19 | 8.0% |
| 4 | BRATTON SOLAR INC | 148 | 84 | 56.8% |
| 5 | FREEDOM FOREVER LLC | 147 | 139 | 94.6% |
| 6 | BRIGHT OPS | 127 | 118 | 92.9% |
| 7 | SOLAR NEGOTIATORS | 107 | 105 | 98.1% |
| 8 | LIFESTYLE SOLAR ELECTRIC | 103 | 1 | 1.0% |
| 9 | Bright Planet Solar | 81 | 22 | 27.2% |
| 10 | Empower Electric Solar | 75 | 69 | 92.0% |
| 11 | SunPower | 69 | 11 | 15.9% |
| 12 | Tesla Energy Operations (formerly SolarCity) | 68 | 66 | 97.1% |
| 13 | SUNNOVA ENERGY CORPORATION | 66 | 46 | 69.7% |
| 14 | GAF Energy | 56 | 56 | 100.0% |
| 15 | GRID Alternatives | 50 | 36 | 72.0% |
Top 15, all Net Billing Tariff installs through Aug 31, 2026. Counts of connected systems, not a rating.
Equipment recorded
In the last 24 months, 3,039 of Visalia’s 3,044 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (762, 25.1%) used modules recorded as Qcells.
In the last 24 months, 3,044 of Visalia’s 3,044 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (1,521, 50.0%) used inverters recorded as Tesla.
In the last 24 months, 2,275 of Visalia’s 3,044 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1,567, 68.9%) used batteries recorded as Tesla.
3,296 of 3,400 battery-paired PG&E and SCE installs (96.9%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Qcells | 762 | 3,348 |
| JA Solar | 678 | 2,212 | |
| LONGi | 540 | 1,423 | |
| Canadian Solar | 361 | 1,180 | |
| Trina Solar | 201 | 598 | |
| Inverter maker | Tesla | 1,521 | 1,840 |
| SolarEdge | 977 | 6,199 | |
| Enphase | 575 | 5,464 | |
| Delta Electronics | 60 | 558 | |
| Qcells | 56 | not in top list | |
| Battery maker | Tesla | 1,567 | 2,032 |
| Enphase | 280 | 400 | |
| SolarEdge | 271 | 359 | |
| FranklinWH | 56 | 105 | |
| LG | 36 | 275 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 15,760 of 18,060 installs, inverters on 18,053. See the methodology and the equipment index.
ZIP codes in Visalia
ZIP codes with their own page where the utilities recorded Visalia on at least 10% of the ZIP’s installs, through Aug 31, 2026.
SGIP battery storage projects in Visalia
The SGIP report lists 314 battery storage projects with the city Visalia, 116 with the status Paid ($2,030,795 in current incentive allocations, 3,196 kWh).
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 116 | 3,196 | $2,030,795 |
| PBI in Process | 8 | 16,870 | $6,560,378 |
| Reserved | 25 | 11,774 | $1,753,080 |
| Pending Reservation | 3 | 40 | $54,704 |
| Waitlist | 9 | 134 | $235,868 |
| Cancelled | 147 | 45,341 | $27,260,130 |
| RRF Rejected | 6 | 80 | $13,383 |
Installers named on the most SGIP storage projects in Visalia
| Installer | Projects | Paid |
|---|---|---|
| GRID Alternatives | 42 | 32 |
| Sunrun | 32 | 16 |
| Tesla | 25 | 5 |
| Semper Solaris Construction Inc | 16 | 11 |
| HAVEN ENERGY SERVICES INC | 12 | 6 |
| FREEDOM FOREVER LLC | 11 | 7 |
| Infinity Energy, Inc | 9 | 5 |
| PetersenDean | 9 | 7 |
| SOLAR 4 AMERICA | 9 | 7 |
| Kuubix Energy Inc. | 7 | 3 |
101 of the 314 projects name no installer with a page in this index, so they are counted above but not in this list.
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
All SGIP battery projects, and SGIP battery incentive money by county.
SolarAPP+ automated permitting
Visalia is on SolarAPP+’s public list of jurisdictions where its automated solar permitting is available, as read on Nov 16, 2026, marked for PV, PV+ST, MPU, MBD. The list gives no start date.
Matched by exact name to the SolarAPP+ public list. A listing says the jurisdiction accepts SolarAPP+ permits; it is not a statement about any installer or permit. All California SolarAPP+ jurisdictions.
At a glance
- Residential solar installs
- 18,060
- Last 24 months
- 3,044
- Capacity
- 143.3 MW DC
- Median system size
- 7 kW DC
- With battery storage
- 18.8% all time; 76.7% last 24 months
- Third-party owned
- 51.9% where reported
- Ownership types recorded
- PPA 6,450, lease 2,083, prepaid lease 22, other 318
- Median battery size
- 13.5 kWh
- Earliest install in data
- Jul 25, 2001
Common questions
How many homes in Visalia have solar?
18,060 residential solar systems in Visalia were interconnected by PG&E, SCE or SDG&E through Aug 31, 2026, 3,044 of them in the last 24 months. Homes on municipal utilities are not included.
How many solar installers work in Visalia?
157 installer names have at least one install interconnected in Visalia in the last 24 months, and 582 appear in the full record.
How common are batteries with new solar in Visalia?
18.8% of the solar installs interconnected in Visalia include battery storage across all years, and 76.7% in the last 24 months (2,334 of 3,044).
How many solar installs in Visalia are under NEM 3.0?
3,934 of the 18,060 residential solar installs in Visalia (21.8% of the 18,060 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 76.5% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.