GB Energy Inc.
How many solar installs has GB Energy Inc. done in California, and which license number is on its installs?
GB Energy Inc. has 62 residential solar installs interconnected in California, active in the records from 2013 through 2015 (Nov 22, 2013 to Mar 25, 2015), most of them in Placer County (40), El Dorado County (11) and San Joaquin County (3). CSLB lists license 977486 (SUNRISE ENERGY SOLUTIONS INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-46, expires Oct 31, 2028.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 62
- Last 24 months
- 0
- Total capacity
- 367.7 kW DC
- Median system size
- 5.6 kW DC
- With battery storage
- 0.0% all time; no installs in the last 24 months last 24 months
- Third-party owned
- 0.0% of 62 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- none recorded
- First install
- Nov 22, 2013
- Latest install
- Mar 25, 2015
- Counties
- 8
- Utilities
- PGE 62
- CSLB license
- 977486
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2013 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2013 | 3 | 0 |
| 2014 | 42 | 0 |
| 2015 | 17 | 0 |
| 2016 | 0 | 0 |
| 2017 | 0 | 0 |
| 2018 | 0 | 0 |
| 2019 | 0 | 0 |
| 2020 | 0 | 0 |
| 2021 | 0 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 62 interconnected installs with a tariff recorded (62) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 62 | 100.0% | not counted |
| NEM 2.0 | 0 | 0.0% | 0 |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on GB Energy Inc.’s installs. No residential system in the file lists a third-party owner name that matches GB Energy Inc. exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 62 of GB Energy Inc.’s 62 installs name a module maker in the “Generator Manufacturer” fields, and most of those (38, 61.3%) used modules recorded as Canadian Solar.
Across all years, 62 of GB Energy Inc.’s 62 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (33, 53.2%) used inverters recorded as Enphase.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Canadian Solar | 0 | 38 |
| Qcells | 0 | 17 | |
| Axitec | 0 | 2 | |
| Shanghai Chaori Solar Energy Science & Technology | 0 | 2 | |
| Sharp | 0 | 1 | |
| Inverter maker | Enphase | 0 | 33 |
| SolarEdge | 0 | 24 | |
| Enecsys | 0 | 4 | |
| SMA | 0 | 1 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 62 of 62 installs, inverters on 62. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 977486 | SUNRISE ENERGY SOLUTIONS INC (Corporation) | CLEAR | B General Building Contractor; C-46 Solar Contractor | Oct 2, 2012 | Oct 31, 2028 | 53 |
License numbers are the ones the utilities recorded on the interconnection applications (56 of 62 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 977486. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Other names reported under the same license
- Sunrise Energy Solutions Inc: 234 installs, license 977486
Counties
| County | Installs |
|---|---|
| Placer | 40 |
| El Dorado | 11 |
| San Joaquin | 3 |
| Sutter | 3 |
| Yolo | 2 |
| Contra Costa | 1 |
| Solano | 1 |
| Yuba | 1 |
Top cities
| City | Installs |
|---|---|
| Rocklin | 19 |
| El Dorado Hills | 9 |
| Granite Bay | 9 |
| Lincoln | 5 |
| Auburn | 4 |
| Tracy | 3 |
| Yuba City | 3 |
| Cameron Park | 2 |
| Antioch | 1 |
| Davis | 1 |
| Fairfield | 1 |
| Loomis | 1 |
| Meadow Vista | 1 |
| Newcastle | 1 |
| Olivehurst | 1 |
Names as recorded by the utilities
The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| GB Energy Inc. | 29 |
| GB ENERGY INC. | 14 |
| GB Energy Inc | 11 |
| GB ENERGY INC | 6 |
| GB Energy | 1 |
| GB Energy, Inc. | 1 |
Common questions
Where does GB Energy Inc. install solar?
Its installs are spread across 8 counties. The most are in Placer County (40 installs), followed by El Dorado County (11).
How often does GB Energy Inc. install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years.
How many GB Energy Inc. installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 62 interconnected installs with a tariff recorded (62) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.