Harmony Air

How many solar installs has Harmony Air done in California, and which license number is on its installs?

Harmony Air has 151 residential solar installs interconnected in California, active in the records from 2012 through 2026 (Mar 9, 2012 to Apr 23, 2026), most of them in Lake County (108), Mendocino County (16) and Sonoma County (12). CSLB lists license 956384 (HARMONY AIR INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, C-20, expires Feb 29, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
151
Last 24 months
9
Total capacity
1,040.3 kW DC
Median system size
6.3 kW DC
With battery storage
17.2% all time; 66.7% last 24 months
Third-party owned
1.3% of 151 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
6 installs, latest Apr 23, 2026
Ownership types recorded
PPA 1, lease 1
Median battery size
18 kWh (19 installs list a capacity)
First install
Mar 9, 2012
Latest install
Apr 23, 2026
Counties
8
Utilities
PGE 151
CSLB license
956384

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2012 to 2026

YearInstalls interconnectedWith battery storage
201220
201360
201450
201550
2016110
201770
2018130
2019150
2020133
2021116
2022278
2023193
202491
202541
2026 (through Aug 31, 2026)44

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

6 of its 151 interconnected installs (4.0% of the 151 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Apr 23, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.02919.2%not counted
NEM 2.011676.8%20 (17.2%)
Net Billing Tariff64.0%6 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 2 of Harmony Air’s installs the utility recorded a third-party ownership type: PPA 1, lease 1, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Harmony Air exactly.

Third-party owner named on its installsInstalls
Sunrun2

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 9 of Harmony Air’s 9 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (3, 33.3%) used modules recorded as Canadian Solar.

In the last 24 months, 9 of Harmony Air’s 9 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (3, 33.3%) used inverters recorded as APsystems (Altenergy Power System).

In the last 24 months, 6 of Harmony Air’s 9 installs name a battery maker in the “Generator Manufacturer” fields, and the most common maker (3, 50.0%) used batteries recorded as Sigenergy.

14 of 26 battery-paired PG&E and SCE installs (53.8%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCanadian Solar3not in top list
Suzhou Talesun Solar Technologies313
JinkoSolar130
Qcells130
Trina Solar1not in top list
Inverter makerAPsystems (Altenergy Power System)319
Sigenergy3not in top list
Enphase175
PointGuard Energy Inc.1not in top list
Sol-Ark112
Battery makerSigenergy33
Enphase14
Lithion Battery Inc.1not in top list
PointGuard Energy Inc.1not in top list

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 150 of 151 installs, inverters on 150. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Harmony Air as developer on 3 battery storage projects and as installer on 3 (3 name it as both), 3 projects in all with 76 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from Sep 8, 2021 to Jun 2, 2022.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Cancelled376$16,014

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Large-Scale Storage266$14,5580$0
Small Residential Storage110$1,4560$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
956384HARMONY AIR INC (Corporation)CLEARC-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning ContractorJan 6, 2011Feb 29, 2028143

License numbers are the ones the utilities recorded on the interconnection applications (143 of 151 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 956384. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Lake108
Mendocino16
Sonoma12
Santa Clara6
San Mateo4
Napa3
Placer1
Yolo1

Top cities

CityInstalls
Kelseyville39
Lakeport26
Cobb10
Clearlake Oaks7
Fort Bragg7
Santa Rosa7
Lower Lake5
Middletown5
Ukiah4
Clearlake3
Hidden Valley Lake3
San Jose3
Windsor3
Calistoga2
Finley2

Names as recorded by the utilities

The utilities recorded this installer under 4 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
HARMONY AIR INC85
Harmony Air60
HARMONY AIR4
Harmony Air Inc2

Common questions

Where does Harmony Air install solar?

Its installs are spread across 8 counties. The most are in Lake County (108 installs), followed by Mendocino County (16).

How often does Harmony Air install batteries with solar?

17.2% of its interconnected solar installs include battery storage across all years, and 66.7% in the last 24 months (6 of 9).

How many Harmony Air installs are under NEM 3.0 (the Net Billing Tariff)?

6 of its 151 interconnected installs (4.0% of the 151 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.