Sunrise 805

How many solar installs has Sunrise 805 done in California, and which license number is on its installs?

Sunrise 805 has 125 residential solar installs interconnected in California, active in the records from 2017 through 2019 (Apr 21, 2017 to Sep 20, 2019), most of them in Santa Barbara County (125). CSLB lists license 1003200 (SUNRISE805) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Apr 30, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
125
Last 24 months
0
Total capacity
297.3 kW DC
Median system size
2.1 kW DC
With battery storage
1.6% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 125 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
Median battery size
10.1 kWh (2 installs list a capacity)
First install
Apr 21, 2017
Latest install
Sep 20, 2019
Counties
1
Utilities
PGE 121, SCE 4
CSLB license
1003200

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2017 to 2026

YearInstalls interconnectedWith battery storage
2017360
2018450
2019442
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 125 interconnected installs with a tariff recorded (125) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.021.6%not counted
NEM 2.012398.4%1 (0.8%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Sunrise 805’s installs. No residential system in the file lists a third-party owner name that matches Sunrise 805 exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 125 of Sunrise 805’s 125 installs name a module maker in the “Generator Manufacturer” fields, and most of those (119, 95.2%) used modules recorded as CertainTeed.

Across all years, 125 of Sunrise 805’s 125 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (123, 98.4%) used inverters recorded as Enphase.

Across all years, 1 of Sunrise 805’s 125 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Tesla.

1 of 2 battery-paired PG&E and SCE installs (50.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCertainTeed0119
LG02
Solaria02
ElectrIQ01
JinkoSolar01
Inverter makerEnphase0123
Darfon Electronics Corp.01
Pika Energy01
Battery makerTesla01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 125 of 125 installs, inverters on 125. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Sunrise 805 as developer on 0 battery storage projects and as installer on 6 (0 name it as both), 6 projects in all with 115 kWh of storage. 5 have the status Paid, with $41,622 in current incentive allocations. Applications were received from Jun 11, 2019 to Jul 26, 2023.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid5103$41,622
Cancelled111$2,328

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage464$15,2224$15,222
Equity Resiliency140$26,4001$26,400
Large-Scale Storage111$2,3280$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1003200SUNRISE805 (Corporation)CLEARC-10 Electrical ContractorApr 27, 2015Apr 30, 2027125

License numbers are the ones the utilities recorded on the interconnection applications (125 of 125 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1003200. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Santa Barbara125

Top cities

CityInstalls
Buellton119
Goleta3
Santa Barbara1
Santa Maria1
Santa Ynez1

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Sunrise 805125

Common questions

Where does Sunrise 805 install solar?

Its installs are spread across 1 county. The most are in Santa Barbara County (125 installs).

How often does Sunrise 805 install batteries with solar?

1.6% of its interconnected solar installs include battery storage across all years.

How many Sunrise 805 installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 125 interconnected installs with a tariff recorded (125) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.