Westcoast Solar Energy
How many solar installs has Westcoast Solar Energy done in California, and which license number is on its installs?
Westcoast Solar Energy has 204 residential solar installs interconnected in California, active in the records from 2010 through 2026 (Jul 7, 2010 to Jan 9, 2026), most of them in Sonoma County (172), Napa County (19) and Marin County (4). CSLB lists license 963158 (WESTCOAST SOLAR ENERGY) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, C-46, expires Jul 31, 2027.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 204
- Last 24 months
- 9
- Total capacity
- 2,470.8 kW DC
- Median system size
- 7.7 kW DC
- With battery storage
- 12.3% all time; 55.6% last 24 months
- Third-party owned
- 0.0% of 204 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 8 installs, latest Jan 9, 2026
- Ownership types recorded
- none recorded
- Median battery size
- 134.8 kWh (2 installs list a capacity)
- First install
- Jul 7, 2010
- Latest install
- Jan 9, 2026
- Counties
- 10
- Utilities
- PGE 204
- CSLB license
- 963158
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2010 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2010 | 4 | 0 |
| 2011 | 7 | 0 |
| 2012 | 2 | 0 |
| 2013 | 2 | 0 |
| 2014 | 17 | 0 |
| 2015 | 10 | 0 |
| 2016 | 8 | 0 |
| 2017 | 14 | 0 |
| 2018 | 13 | 0 |
| 2019 | 16 | 0 |
| 2020 | 24 | 5 |
| 2021 | 29 | 6 |
| 2022 | 22 | 3 |
| 2023 | 23 | 3 |
| 2024 | 5 | 4 |
| 2025 | 6 | 2 |
| 2026 (through Aug 31, 2026) | 2 | 2 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
8 of its 204 interconnected installs (3.9% of the 204 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Jan 9, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 52 | 25.5% | not counted |
| NEM 2.0 | 144 | 70.6% | 16 (11.1%) |
| Net Billing Tariff | 8 | 3.9% | 8 (100.0%) |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Westcoast Solar Energy’s installs. No residential system in the file lists a third-party owner name that matches Westcoast Solar Energy exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 9 of Westcoast Solar Energy’s 9 installs name a module maker in the “Generator Manufacturer” fields, and most of those (7, 77.8%) used modules recorded as Hyundai.
In the last 24 months, 9 of Westcoast Solar Energy’s 9 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (9, 100.0%) used inverters recorded as Enphase.
In the last 24 months, 5 of Westcoast Solar Energy’s 9 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (5, 100.0%) used batteries recorded as Enphase.
21 of 25 battery-paired PG&E and SCE installs (84.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Hyundai | 7 | 31 |
| LG | 1 | 101 | |
| Qcells | 1 | not in top list | |
| Inverter maker | Enphase | 9 | 115 |
| Battery maker | Enphase | 5 | 16 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 188 of 204 installs, inverters on 204. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names Westcoast Solar Energy as developer on 0 battery storage projects and as installer on 3 (0 name it as both), 3 projects in all with 115 kWh of storage. 1 have the status Paid, with $19,412 in current incentive allocations. Applications were received from Feb 23, 2016 to Aug 5, 2020.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 1 | 19 | $19,412 |
| Cancelled | 2 | 95 | $42,338 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Equity Resiliency | 1 | 19 | $19,412 | 1 | $19,412 |
| Large-Scale Storage | 1 | 75 | $29,238 | 0 | $0 |
| Not stated | 1 | 20 | $13,100 | 0 | $0 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 963158 | WESTCOAST SOLAR ENERGY (Corporation) | CLEAR | C-10 Electrical Contractor; C-46 Solar Contractor | Jul 12, 2011 | Jul 31, 2027 | 181 |
License numbers are the ones the utilities recorded on the interconnection applications (181 of 204 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 963158. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Other names reported under the same license
- West Coast Solar Energy: 90 installs, license 963158
Counties
Top cities
| City | Installs |
|---|---|
| Santa Rosa | 70 |
| Rohnert Park | 20 |
| Healdsburg | 16 |
| Petaluma | 13 |
| Sebastopol | 12 |
| Windsor | 10 |
| Napa | 9 |
| Cotati | 7 |
| Saint Helena | 5 |
| Sonoma | 5 |
| Glen Ellen | 4 |
| Bodega Bay | 3 |
| Calistoga | 3 |
| Penngrove | 3 |
| Geyserville | 2 |
Names as recorded by the utilities
The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| WESTCOAST SOLAR ENERGY | 114 |
| Westcoast Solar Energy | 90 |
Common questions
Where does Westcoast Solar Energy install solar?
Its installs are spread across 10 counties. The most are in Sonoma County (172 installs), followed by Napa County (19).
How often does Westcoast Solar Energy install batteries with solar?
12.3% of its interconnected solar installs include battery storage across all years, and 55.6% in the last 24 months (5 of 9).
How many Westcoast Solar Energy installs are under NEM 3.0 (the Net Billing Tariff)?
8 of its 204 interconnected installs (3.9% of the 204 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
- Self-Generation Incentive Program (SGIP) program administrators: Real-Time Public Report of SGIP applications (selfgenca.com)
Records last pulled Nov 16, 2026. Every entry links to the original public record.