Home solar in ZIP code 95722, California
Service city recorded on most installs: Meadow Vista. County: Placer County.
How many homes in ZIP code 95722 have solar?
PG&E, SCE and SDG&E interconnected 491 residential solar systems in ZIP code 95722 through Aug 31, 2026, 84 of them in the last 24 months (Sep 2024 through Aug 2026). The utilities recorded Meadow Vista, Placer County, as the service city on 491 of them. Tesla Energy Operations (formerly SolarCity) has the most installs recorded in this ZIP, 27.
Counts of interconnected systems from utility records, not a rating of any installer.
Data: California DG Stats interconnection records (Interconnected_Project_Sites_2026-08-31.zip), which run through Aug 31, 2026. ZIP codes are the service ZIP the utility recorded on each project.
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
At a glance
- Residential solar installs
- 491
- Last 24 months
- 84 (Sep 2024 through Aug 2026)
- Capacity
- 4,300.5 kW DC
- Median system size
- 7.9 kW DC
- Net Billing Tariff (NEM 3.0)
- 79 installs, 16.1% of those with a tariff recorded
- Utility
- PGE 491
- First install in data
- Jun 17, 2002
- Latest install in data
- Aug 21, 2026
Installs by year
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2002 | 1 | 0 |
| 2003 | 1 | 0 |
| 2004 | 3 | 0 |
| 2005 | 0 | 0 |
| 2006 | 2 | 0 |
| 2007 | 2 | 0 |
| 2008 | 4 | 0 |
| 2009 | 10 | 0 |
| 2010 | 5 | 0 |
| 2011 | 3 | 0 |
| 2012 | 9 | 0 |
| 2013 | 14 | 0 |
| 2014 | 15 | 0 |
| 2015 | 32 | 0 |
| 2016 | 33 | 0 |
| 2017 | 24 | 0 |
| 2018 | 25 | 0 |
| 2019 | 26 | 1 |
| 2020 | 36 | 7 |
| 2021 | 29 | 6 |
| 2022 | 52 | 11 |
| 2023 | 58 | 6 |
| 2024 | 42 | 24 |
| 2025 | 39 | 17 |
| 2026 (through Aug 31, 2026) | 26 | 12 |
Battery storage
17.1% of the residential solar installs here include battery storage across all years (84 of 491). In the last 24 months the share was 50.0% (42 of 84).
Net metering tariff
Of the 491 installs with a net metering tariff recorded: NEM 1.0 138 (28.1%), NEM 2.0 274 (55.8%), the Net Billing Tariff (often called NEM 3.0) 79 (16.1%). The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023, under CPUC Decision D.22-12-056.
Lease, PPA or owned
10.4% of the 491 installs with ownership recorded are third-party owned (a lease or power purchase agreement); the other 440 are recorded as not third-party owned. Ownership types recorded: PPA 42, lease 9.
Installers by installs in 95722
Installers with a page in this index, most installs in this ZIP first. 112 such installers have at least one install here. 51 more installs were by 39 installer names without a page in this index. 24 were self-installed or had no installer recorded. Counts of connected systems, not a rating.
| Installer | Installs in 95722 | Last 24 months |
|---|---|---|
| Tesla Energy Operations (formerly SolarCity) | 27 | 0 |
| RT Solar | 24 | 0 |
| Sunrun | 21 | 4 |
| Economic Energy Solutions Inc. | 19 | 3 |
| Hooked On Solar | 18 | 3 |
| Magic Sun Solar, Inc. | 18 | 3 |
| California Solar Electric | 15 | 1 |
| V3 Electric | 12 | 4 |
| Matson-Services | 11 | 0 |
| ELECTRIC REVOLUTION | 9 | 3 |
City and county recorded for 95722
The Service City and Service County the utilities entered on this ZIP’s installs, as recorded. No outside ZIP directory is used.
| Recorded as | Installs |
|---|---|
| City: Meadow Vista | 491 |
| County: Placer County | 491 |
Common questions
How common are home batteries with solar in 95722?
17.1% of the residential solar installs here include battery storage across all years (84 of 491). In the last 24 months the share was 50.0% (42 of 84).
How many solar installs in 95722 are under NEM 3.0?
79 of the 491 installs here with a tariff recorded (16.1%) were interconnected under the Net Billing Tariff, often called NEM 3.0, which applies to interconnection applications submitted on or after April 15, 2023.
Which solar installers have the most installs in 95722?
Among installers with a page in this index, by installs interconnected here through Aug 31, 2026: Tesla Energy Operations (formerly SolarCity) (27), RT Solar (24), Sunrun (21). These are counts of connected systems, not a rating of price, workmanship or service.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.