Desert Solar Electric has 54 residential solar installs interconnected in California, active in the records from 2015 through 2025 (Jun 26, 2015 to Dec 23, 2025), most of them in Riverside County (54). CSLB lists license 845653 (sole owner license, name not shown) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Aug 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
54
Last 24 months
4
Total capacity
622.5 kW DC
Median system size
9.6 kW DC
With battery storage
1.9% all time; 25.0% last 24 months
Third-party owned
0.0% of 54 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
3 installs, latest Sep 16, 2025
Ownership types recorded
none recorded
Median battery size
7 kWh (1 installs list a capacity)
First install
Jun 26, 2015
Latest install
Dec 23, 2025
Counties
1
Utilities
SCE 54
CSLB license
845653

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2015 to 2026

YearInstalls interconnectedWith battery storage
201550
201670
201740
201850
201930
202020
202120
2022110
202390
202420
202541
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

3 of its 54 interconnected installs (5.6% of the 54 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 33.3% of those include battery storage. The latest Net Billing Tariff install was approved Sep 16, 2025.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.01324.1%not counted
NEM 2.03870.4%0 (0.0%)
Net Billing Tariff35.6%1 (33.3%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Desert Solar Electric’s installs. No residential system in the file lists a third-party owner name that matches Desert Solar Electric exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 4 of Desert Solar Electric’s 4 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (1, 25.0%) used modules recorded as Canadian Solar.

In the last 24 months, 4 of Desert Solar Electric’s 4 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (4, 100.0%) used inverters recorded as Enphase.

In the last 24 months, 1 of Desert Solar Electric’s 4 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Enphase.

1 of 1 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCanadian Solar130
Qcells118
VSUN (Vietnam Sunergy)11
Znshine1not in top list
Inverter makerEnphase417
Battery makerEnphase11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 53 of 54 installs, inverters on 54. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
845653Sole owner license (name not shown)CLEARC-10 Electrical ContractorAug 31, 2004Aug 31, 202854

License numbers are the ones the utilities recorded on the interconnection applications (54 of 54 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 845653. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Riverside54

Top cities

CityInstalls
Palm Desert17
Palm Springs14
Rancho Mirage12
Cathedral City8
Desert Hot Springs2
Indian Wells1

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
DESERT SOLAR ELECTRIC42
Desert Solar Electric12

Common questions

Where does Desert Solar Electric install solar?

Its installs are spread across 1 county. The most are in Riverside County (54 installs).

How often does Desert Solar Electric install batteries with solar?

1.9% of its interconnected solar installs include battery storage across all years, and 25.0% in the last 24 months (1 of 4).

How many Desert Solar Electric installs are under NEM 3.0 (the Net Billing Tariff)?

3 of its 54 interconnected installs (5.6% of the 54 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 33.3% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.