Vista Solar, Inc.
How many solar installs has Vista Solar, Inc. done in California, and which license number is on its installs?
Vista Solar, Inc. has 47 residential solar installs interconnected in California, active in the records from 2008 through 2021 (Jul 8, 2008 to Dec 7, 2021), most of them in Santa Clara County (28), Alameda County (5) and San Diego County (4). The utilities did not record a CSLB license number on enough of these installs to look one up.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 47
- Last 24 months
- 0
- Total capacity
- 481 kW DC
- Median system size
- 4.7 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
- Third-party owned
- 0.0% of 47 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- none recorded
- First install
- Jul 8, 2008
- Latest install
- Dec 7, 2021
- Counties
- 9
- Utilities
- PGE 43, SDGE 4
- CSLB license
- none reported
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2008 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2008 | 2 | 0 |
| 2009 | 13 | 0 |
| 2010 | 16 | 0 |
| 2011 | 6 | 0 |
| 2012 | 1 | 0 |
| 2013 | 1 | 0 |
| 2014 | 0 | 0 |
| 2015 | 0 | 0 |
| 2016 | 1 | 0 |
| 2017 | 0 | 0 |
| 2018 | 1 | 0 |
| 2019 | 0 | 0 |
| 2020 | 3 | 0 |
| 2021 | 3 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 47 interconnected installs with a tariff recorded (47) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 40 | 85.1% | not counted |
| NEM 2.0 | 7 | 14.9% | 0 (0.0%) |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Vista Solar, Inc.’s installs. No residential system in the file lists a third-party owner name that matches Vista Solar, Inc. exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 46 of Vista Solar, Inc.’s 47 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (22, 47.8%) used modules recorded as Suntech.
Across all years, 47 of Vista Solar, Inc.’s 47 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (23, 48.9%) used inverters recorded as SMA.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Suntech | 0 | 22 |
| SunPower | 0 | 19 | |
| DelSolar | 0 | 1 | |
| Evergreen Solar | 0 | 1 | |
| LG | 0 | 1 | |
| Inverter maker | SMA | 0 | 23 |
| SunPower | 0 | 12 | |
| SolarEdge | 0 | 6 | |
| Enphase | 0 | 3 | |
| Power-One | 0 | 2 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 46 of 47 installs, inverters on 47. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names Vista Solar, Inc. as developer on 1 battery storage project and as installer on 1 (1 name it as both), 1 projects in all with 496 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from Sep 28, 2020 to Sep 28, 2020.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| PBI in Process | 1 | 496 | $124,000 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Large-Scale Storage | 1 | 496 | $124,000 | 0 | $0 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
The utilities did not record a license number for enough of these installs to look one up.
License numbers are the ones the utilities recorded on the interconnection applications (8 of 47 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it.
Counties
| County | Installs |
|---|---|
| Santa Clara | 28 |
| Alameda | 5 |
| San Diego | 4 |
| San Mateo | 4 |
| Marin | 2 |
| Contra Costa | 1 |
| San Benito | 1 |
| San Francisco | 1 |
| Santa Cruz | 1 |
Top cities
| City | Installs |
|---|---|
| San Jose | 11 |
| Morgan Hill | 4 |
| Sunnyvale | 4 |
| Cupertino | 3 |
| Vista | 3 |
| Berkeley | 2 |
| San Rafael | 2 |
| Aptos | 1 |
| Byron | 1 |
| Campbell | 1 |
| Fremont | 1 |
| Gilroy | 1 |
| Half Moon Bay | 1 |
| Los Altos Hills | 1 |
| Los Gatos | 1 |
Names as recorded by the utilities
The utilities recorded this installer under 7 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Vista Solar, Inc. | 27 |
| Vista Solar, Inc | 6 |
| Vista Solar Inc | 5 |
| Vista Solar Inc. | 4 |
| Vista Solar | 3 |
| Vista Solar inc. | 1 |
| Vista-Solar Inc | 1 |
Common questions
Where does Vista Solar, Inc. install solar?
Its installs are spread across 9 counties. The most are in Santa Clara County (28 installs), followed by Alameda County (5).
How often does Vista Solar, Inc. install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many Vista Solar, Inc. installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 47 interconnected installs with a tariff recorded (47) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
- Self-Generation Incentive Program (SGIP) program administrators: Real-Time Public Report of SGIP applications (selfgenca.com)
Records last pulled Nov 16, 2026. Every entry links to the original public record.