CGS Energy Consultants
How many solar installs has CGS Energy Consultants done in California, and which license number is on its installs?
CGS Energy Consultants has 121 residential solar installs interconnected in California, active in the records from 2015 through 2026 (Jul 22, 2015 to Aug 12, 2026), most of them in San Diego County (118) and Orange County (3). CSLB lists license 699151 (DANA LOGSDON ROOFING & SOLAR INCORPORATED) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-39, C-46, expires Jul 31, 2028.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
The installs credited to CGS Energy Consultants here carry more than one CSLB license number: 699151 on 75 (CSLB holder DANA LOGSDON ROOFING & SOLAR INCORPORATED, El Cajon) and 1005207 on 28 (not found in the CSLB License Master file), in the License Master file pulled Nov 4, 2026. They are grouped under one installer by the name written on the applications; the records do not say whether these numbers belong to the same legal entity.
- Interconnected installs
- 121
- Last 24 months
- 7
- Total capacity
- 847 kW DC
- Median system size
- 6.4 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
- Third-party owned
- 0.0% of 121 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 2 installs, latest Aug 12, 2026
- Ownership types recorded
- none recorded
- First install
- Jul 22, 2015
- Latest install
- Aug 12, 2026
- Counties
- 2
- Utilities
- SDGE 119, SCE 2
- CSLB license
- 699151, 1005207
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2015 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2015 | 7 | 0 |
| 2016 | 10 | 0 |
| 2017 | 8 | 0 |
| 2018 | 10 | 0 |
| 2019 | 3 | 0 |
| 2020 | 0 | 0 |
| 2021 | 2 | 0 |
| 2022 | 22 | 0 |
| 2023 | 46 | 0 |
| 2024 | 8 | 0 |
| 2025 | 4 | 0 |
| 2026 (through Aug 31, 2026) | 1 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
2 of its 121 interconnected installs (1.7% of the 121 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Aug 12, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 15 | 12.4% | not counted |
| NEM 2.0 | 104 | 86.0% | not recorded |
| Net Billing Tariff | 2 | 1.7% | not recorded |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on CGS Energy Consultants’s installs. No residential system in the file lists a third-party owner name that matches CGS Energy Consultants exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 6 of CGS Energy Consultants’ 7 installs name a module maker in the “Generator Manufacturer” fields, and most of those (4, 66.7%) used modules recorded as REC.
In the last 24 months, 7 of CGS Energy Consultants’ 7 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (7, 100.0%) used inverters recorded as Enphase.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | REC | 4 | 50 |
| Panasonic | 1 | not in top list | |
| Qcells | 1 | 4 | |
| Inverter maker | Enphase | 7 | 92 |
| SMA | 1 | 8 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 118 of 121 installs, inverters on 121. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 699151 | DANA LOGSDON ROOFING & SOLAR INCORPORATED (Corporation) | CLEAR | B General Building Contractor; C-39 Roofing Contractor; C-46 Solar Contractor | Nov 17, 1994 | Jul 31, 2028 | 75 |
| 1005207 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 28 | ||||
License numbers are the ones the utilities recorded on the interconnection applications (111 of 121 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 699151. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Local solar permits naming its license
Solar permits in city and county open data that list CGS Energy Consultants’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2022 | 2023 | 2024 | 2025 | Total |
|---|---|---|---|---|---|---|
| unincorporated San Diego County | 699151 | 5 | 9 | 3 | 1 | 18 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Counties
Top cities
| City | Installs |
|---|---|
| San Diego | 45 |
| El Cajon | 16 |
| La Jolla | 9 |
| Alpine | 8 |
| Encinitas | 5 |
| Escondido | 5 |
| La Mesa | 5 |
| Lakeside | 4 |
| Coronado | 3 |
| Oceanside | 3 |
| Poway | 3 |
| Bonita | 2 |
| Imperial Beach | 2 |
| Rancho Santa Fe | 2 |
| Santee | 2 |
Names as recorded by the utilities
The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| CGS Energy Consultants | 121 |
Common questions
Where does CGS Energy Consultants install solar?
Its installs are spread across 2 counties. The most are in San Diego County (118 installs), followed by Orange County (3).
How often does CGS Energy Consultants install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many CGS Energy Consultants installs are under NEM 3.0 (the Net Billing Tariff)?
2 of its 121 interconnected installs (1.7% of the 121 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.