Gilmore Heating & Air

How many solar installs has Gilmore Heating & Air done in California, and which license number is on its installs?

Gilmore Heating & Air has 190 residential solar installs interconnected in California, active in the records from 2009 through 2019 (Dec 14, 2009 to Sep 30, 2019), most of them in El Dorado County (131), Amador County (31) and Placer County (23). CSLB lists license 559305 (GILMORE HOME SERVICES) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-20, C-36, expires Sep 30, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
190
Last 24 months
0
Total capacity
1,240.5 kW DC
Median system size
6.1 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 190 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Dec 14, 2009
Latest install
Sep 30, 2019
Counties
6
Utilities
PGE 190
CSLB license
559305

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2009 to 2026

YearInstalls interconnectedWith battery storage
200910
201010
201100
201200
201300
201400
201500
2016180
2017640
2018880
2019180
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 190 interconnected installs with a tariff recorded (190) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.02111.1%not counted
NEM 2.016988.9%0 (0.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Gilmore Heating & Air’s installs. No residential system in the file lists a third-party owner name that matches Gilmore Heating & Air exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 190 of Gilmore Heating & Air’s 190 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (93, 48.9%) used modules recorded as Qcells.

Across all years, 190 of Gilmore Heating & Air’s 190 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (101, 53.2%) used inverters recorded as SolarEdge.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells093
SolarWorld069
LG012
Solaria05
Panasonic03
Inverter makerSolarEdge0101
Enphase082
Fronius05
CFM Equipment Distributors Inc01
SMA01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 190 of 190 installs, inverters on 190. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
559305GILMORE HOME SERVICES (Limited Liability)CLEARC-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-36Mar 6, 1989Sep 30, 2028187

License numbers are the ones the utilities recorded on the interconnection applications (188 of 190 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 559305. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
El Dorado131
Amador31
Placer23
Calaveras3
Sutter1
Yolo1

Top cities

CityInstalls
Placerville47
El Dorado Hills20
Cameron Park15
Shingle Springs12
El Dorado11
Ione10
Rescue9
Lincoln6
Auburn5
Rocklin5
Camino4
Pioneer4
Sutter Creek4
Fiddletown3
Garden Valley3

Names as recorded by the utilities

The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Gilmore Heating & Air184
Gilmore Heating and Air2
GILMORE HEATING AND AIR2
Gilmore Heating & Air/1
Gilmore Heating And Air1

Common questions

Where does Gilmore Heating & Air install solar?

Its installs are spread across 6 counties. The most are in El Dorado County (131 installs), followed by Amador County (31).

How often does Gilmore Heating & Air install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many Gilmore Heating & Air installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 190 interconnected installs with a tariff recorded (190) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.