JKB Energy has 43 residential solar installs interconnected in California, active in the records from 2013 through 2025 (Jan 31, 2013 to Oct 6, 2025), most of them in San Joaquin County (15), Kern County (7) and Merced County (7). CSLB lists license 991112 (J K B ENERGY CORPORATION) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-46, expires Mar 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
43
Last 24 months
2
Total capacity
1,649.6 kW DC
Median system size
11.8 kW DC
With battery storage
0.0% all time; 0.0% last 24 months
Third-party owned
0.0% of 41 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Jan 31, 2013
Latest install
Oct 6, 2025
Counties
9
Utilities
PGE 37, SCE 6
CSLB license
991112

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2013 to 2026

YearInstalls interconnectedWith battery storage
201320
201450
201570
2016110
201760
201820
201980
202000
202100
202200
202300
202400
202520
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 43 interconnected installs with a tariff recorded (43) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.02660.5%not counted
NEM 2.01739.5%0 (0.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on JKB Energy’s installs. No residential system in the file lists a third-party owner name that matches JKB Energy exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 2 of JKB Energy’s 2 installs name a module maker in the “Generator Manufacturer” fields, and most of those (2, 100.0%) used modules recorded as Sunergy California.

In the last 24 months, 2 of JKB Energy’s 2 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (2, 100.0%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSunergy California2not in top list
Inverter makerEnphase26

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 41 of 43 installs, inverters on 43. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names JKB Energy as developer on 1 battery storage project and as installer on 1 (1 name it as both), 1 projects in all with 1,252 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from Mar 29, 2021 to Mar 29, 2021.

By status

Status as publishedProjectsStorage kWhCurrent incentive
PBI in Process11,252$275,352

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Large-Scale Storage11,252$275,3520$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
991112J K B ENERGY CORPORATION (Corporation)CLEARB General Building Contractor; C-46 Solar ContractorMar 7, 2014Mar 31, 202830

License numbers are the ones the utilities recorded on the interconnection applications (38 of 43 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 991112. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
San Joaquin15
Kern7
Merced7
Fresno4
Kings3
Sonoma3
Tulare2
Glenn1
Stanislaus1

Top cities

CityInstalls
Ripon8
Snelling4
Fresno3
Windsor3
Delano2
Escalon2
Lemoore2
Manteca2
Merced2
Wasco2
Atwater1
Bakersfield1
Buttonwillow1
Caruthers1
Glennville1

Names as recorded by the utilities

The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
JKB Energy20
JKB Energy Corporation14
JKB Energy Corp4
JKB ENERGY CORPORATION3
JKB Energy Corp.2

Common questions

Where does JKB Energy install solar?

Its installs are spread across 9 counties. The most are in San Joaquin County (15 installs), followed by Kern County (7).

How often does JKB Energy install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years, and 0.0% in the last 24 months (0 of 2).

How many JKB Energy installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 43 interconnected installs with a tariff recorded (43) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.