ALLIANZ HEATING AND AIR

How many solar installs has ALLIANZ HEATING AND AIR done in California, and which license number is on its installs?

ALLIANZ HEATING AND AIR has 128 residential solar installs interconnected in California, active in the records from 2022 through 2026 (Jun 17, 2022 to Feb 17, 2026), most of them in Butte County (108), Tehama County (9) and Glenn County (3). CSLB lists license 510286 (ROYAL AIRE INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-2, C-10, C-20, C-36, C-46, expires Jul 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
128
Last 24 months
1
Total capacity
957.1 kW DC
Median system size
7.6 kW DC
With battery storage
1.6% all time; 100.0% last 24 months
Third-party owned
0.0% of 128 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
1 installs, latest Feb 17, 2026
Ownership types recorded
none recorded
Median battery size
1 kWh (1 installs list a capacity)
First install
Jun 17, 2022
Latest install
Feb 17, 2026
Counties
6
Utilities
PGE 128
CSLB license
510286

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2022 to 2026

YearInstalls interconnectedWith battery storage
2022920
2023351
202400
202500
2026 (through Aug 31, 2026)11

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

1 of its 128 interconnected installs (0.8% of the 128 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Feb 17, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.012799.2%1 (0.8%)
Net Billing Tariff10.8%1 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on ALLIANZ HEATING AND AIR’s installs. No residential system in the file lists a third-party owner name that matches ALLIANZ HEATING AND AIR exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 1 of ALLIANZ HEATING AND AIR’s 1 installs name a module maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used modules recorded as Znshine.

In the last 24 months, 1 of ALLIANZ HEATING AND AIR’s 1 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (1, 100.0%) used inverters recorded as Tesla.

In the last 24 months, 1 of ALLIANZ HEATING AND AIR’s 1 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Tesla.

2 of 2 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerZnshine1not in top list
Inverter makerTesla11
Battery makerTesla11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 127 of 128 installs, inverters on 128. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
510286ROYAL AIRE INC (Corporation)CLEARB General Building Contractor; C-2; C-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-36; C-46 Solar ContractorMay 7, 1987Jul 31, 2028127

License numbers are the ones the utilities recorded on the interconnection applications (128 of 128 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 510286. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Butte108
Tehama9
Glenn3
Shasta3
Sutter3
Yuba2

Top cities

CityInstalls
Chico72
Paradise16
Oroville10
Durham8
Corning6
Orland3
Anderson2
Live Oak2
Los Molinos2
Olivehurst2
Cohasset1
Magalia1
Red Bluff1
Redding1
Yuba City1

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
ALLIANZ HEATING AND AIR127
ALLIANZ HEATING & AIR INC1

Common questions

Where does ALLIANZ HEATING AND AIR install solar?

Its installs are spread across 6 counties. The most are in Butte County (108 installs), followed by Tehama County (9).

How often does ALLIANZ HEATING AND AIR install batteries with solar?

1.6% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (1 of 1).

How many ALLIANZ HEATING AND AIR installs are under NEM 3.0 (the Net Billing Tariff)?

1 of its 128 interconnected installs (0.8% of the 128 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.