LEMONDROP SOLAR

How many solar installs has LEMONDROP SOLAR done in California, and which license number is on its installs?

LEMONDROP SOLAR has 183 residential solar installs interconnected in California, active in the records from 2023 through 2025 (Jun 8, 2023 to Apr 19, 2025), most of them in San Bernardino County (86), Riverside County (85) and Orange County (6). CSLB lists license 1101978 (LEMONDROP SOLAR) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Mar 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
183
Last 24 months
2
Total capacity
1,507.1 kW DC
Median system size
8 kW DC
With battery storage
51.7% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 50.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
68.9% of 183 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
96 installs, latest Apr 19, 2025
Ownership types recorded
PPA 96, lease 30
Median battery size
6.7 kWh (93 installs list a capacity)
First install
Jun 8, 2023
Latest install
Apr 19, 2025
Counties
6
Utilities
SCE 179, SDGE 3, PGE 1
CSLB license
1101978

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2023 to 2026

YearInstalls interconnectedWith battery storage
202315063
20243129
202521
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

96 of its 183 interconnected installs (52.5% of the 183 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 92.6% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Apr 19, 2025.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.08747.5%5 (5.9%)
Net Billing Tariff9652.5%88 (92.6%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 126 of LEMONDROP SOLAR’s installs the utility recorded a third-party ownership type: PPA 96, lease 30, prepaid lease 0, other 0. Across all installers, 9 residential systems list a third-party owner name that matches LEMONDROP SOLAR exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Sunnova59
Everbright54
LEMONDROP SOLAR9
Lemondropsolar1
Lightreach1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 2 of LEMONDROP SOLAR’s 2 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (1, 50.0%) used modules recorded as LG.

In the last 24 months, 2 of LEMONDROP SOLAR’s 2 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (2, 100.0%) used inverters recorded as Enphase.

In the last 24 months, 1 of LEMONDROP SOLAR’s 2 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Enphase.

92 of 93 battery-paired PG&E and SCE installs (98.9%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerLG1not in top list
Qcells1109
SEG Solar1not in top list
Inverter makerEnphase2126
Battery makerEnphase181

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 183 of 183 installs, inverters on 183. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names LEMONDROP SOLAR as developer on 1 battery storage project and as installer on 2 (1 name it as both), 2 projects in all with 27 kWh of storage. 1 have the status Paid, with $13,600 in current incentive allocations. Applications were received from Aug 28, 2024 to Nov 27, 2024.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid114$13,600
Cancelled114$2,040

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency114$13,6001$13,600
Small Residential Storage114$2,0400$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1101978LEMONDROP SOLAR (Corporation)CLEARC-10 Electrical ContractorMar 1, 2023Mar 31, 2027183

License numbers are the ones the utilities recorded on the interconnection applications (183 of 183 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1101978. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list LEMONDROP SOLAR’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2023Total
unincorporated San Diego County110197833

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
San Bernardino86
Riverside85
Orange6
Los Angeles4
El Dorado1
San Diego1

Top cities

CityInstalls
Fontana24
Moreno Valley11
Corona10
San Jacinto10
Ontario9
San Bernardino9
Menifee7
Winchester7
Chino6
Hesperia6
Riverside6
Lake Elsinore5
Norco5
Perris5
Victorville5

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
LEMONDROP SOLAR180
Lemondrop Solar3

Common questions

Where does LEMONDROP SOLAR install solar?

Its installs are spread across 6 counties. The most are in San Bernardino County (86 installs), followed by Riverside County (85).

How often does LEMONDROP SOLAR install batteries with solar?

51.7% of its interconnected solar installs include battery storage across all years, and 50.0% in the last 24 months (1 of 2). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many LEMONDROP SOLAR installs are under NEM 3.0 (the Net Billing Tariff)?

96 of its 183 interconnected installs (52.5% of the 183 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 92.6% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.