Solar installers in Corona, California

Most installs here are in Riverside County.

Who installs the most solar in Corona?

Ranked by interconnected installs in the last 24 months (Sep 2024 through Aug 2026), the top three installers in Corona are Sunrun (677), Tesla Energy Operations (formerly SolarCity) (170) and SunPower (168). They account for 1,015 of the 2,184 residential solar installs interconnected there in that window.

In all, 17,965 homes in Corona have residential solar interconnected by PG&E, SCE or SDG&E through Aug 31, 2026. These are counts of connected systems, not a rating of any installer.

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installers ranked by interconnected installs, last 24 months

Sep 2024 through Aug 2026. Top 25 of 220 installers with installs in this window. 25 installs in the window were self-installed or had no installer recorded.

1Sunrun6771,897
2Tesla Energy Operations (formerly SolarCity)1702,367
3SunPower1681,909
4BRIGHT OPS123164
5FREEDOM FOREVER LLC72449
6V3 Electric49189
7Empower Electric Solar4659
8SUNNOVA ENERGY CORPORATION35188
9SolarMax Renewable Energy Provider, Inc31428
10ORANGE COUNTY CONTRACTING SERVICES3063
11Complete Solar29121
12Current Home25154
13BETTER EARTH ELECTRIC INC24140
14ENERGY SERVICE PARTNERS INC DBA ESP CONTRACTING24229
15LGCY INSTALLATION SERVICES LLC DBA LGCY ELECTRIC2334
16FREEDOM FOREVER SOUTHERN CALIFORNIA LLC2121
17LUXOR ENERGY INC2132
18Powur PBC (Powur Home)21100
19TIMEPROOFUSA2121
20MY SMART HOUSE LLC1717
21Solar Optimum Inc.1798
22SKYLINE SMART ENERGY1524
23AXIA SOLAR CORP1313
24EXO Energy1353
25Semper Solaris Construction Inc13241

Most installs, all time

1Tesla Energy Operations (formerly SolarCity)2,3672,367
2SunPower1,9091,909
3Sunrun1,8971,897
4FREEDOM FOREVER LLC449449
5SolarMax Renewable Energy Provider, Inc428428
6Horizon Solar Power379379
7Solcius346346
8SunStreet Energy Group LLC336336
9Vivint Solar Developer, LLC336336
10Verengo307307

Installs by year

YearInstalls interconnectedWith battery storage
20221,907220
20232,415371
20241,398769
20251,121834
2026 (through Aug 31, 2026)674535

Under the Net Billing Tariff (NEM 3.0)

2,559 of the 17,965 residential solar installs in Corona (14.2% of the 17,965 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 78.2% of those include battery storage. The latest was approved Aug 31, 2026. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023, under CPUC Decision D.22-12-056.

Installers ranked by Net Billing Tariff installs in Corona

1Sunrun76061981.4%
2Tesla Energy Operations (formerly SolarCity)20318390.1%
3SunPower1652716.4%
4BRIGHT OPS16415493.9%
5FREEDOM FOREVER LLC11811194.1%
6V3 Electric616098.4%
7Empower Electric Solar545194.4%
8BETTER EARTH ELECTRIC INC414097.6%
9Current Home3535100.0%
10LUXOR ENERGY INC321546.9%
11LGCY INSTALLATION SERVICES LLC DBA LGCY ELECTRIC312890.3%
12ENERGY SERVICE PARTNERS INC DBA ESP CONTRACTING302996.7%
13ORANGE COUNTY CONTRACTING SERVICES2929100.0%
14Bright Planet Solar28828.6%
15Solar Optimum Inc.252496.0%

Top 15, all Net Billing Tariff installs through Aug 31, 2026. Counts of connected systems, not a rating.

Equipment recorded

In the last 24 months, 2,166 of Corona’s 2,184 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (1,011, 46.7%) used modules recorded as Qcells.

In the last 24 months, 2,184 of Corona’s 2,184 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (895, 41.0%) used inverters recorded as Tesla.

In the last 24 months, 1,580 of Corona’s 2,184 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1,044, 66.1%) used batteries recorded as Tesla.

3,028 of 3,115 battery-paired PG&E and SCE installs (97.2%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells1,0113,983
LONGi269934
JA Solar247654
Canadian Solar130866
Silfab109not in top list
Inverter makerTesla8951,202
Enphase8506,118
SolarEdge4535,605
SunPower451,683
ABB351,212
Battery makerTesla1,0441,640
Enphase252427
SolarEdge198331
FranklinWH3748
LG15337

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 14,628 of 17,965 installs, inverters on 17,961. See the methodology and the equipment index.

Solar permits issued in the City of Corona

From The City of Corona’s open data: CorStat - Building Permits, corstat.coronaca.gov dataset 2agx-camz. Counted by calendar year of the issued field. Solar: permittype = 'ELECTRICAL RESIDENTIAL' with permitsubtype 'SOLAR PANELS-PHOTOVOLTAIC SYSTEM', 'SOLAR PV WITH ESS' or 'PHOTOVOLTAIC SYSTEM', or permittype = 'SYMBIUM SOLAR' (the city’s automated solar permit). Battery: those solar permits with permitsubtype 'SOLAR PV WITH ESS' or 'WITH ESS', or a description that mentions BATTER, ENERGY STORAGE or POWERWALL (any case). Latest solar permit issue date in the data: Oct 15, 2026. Checked Nov 16, 2026.

YearSolar permitsBattery permits
20187261
20197758
202082210
20211,07736
20221,65224
20231,71126
2024882213
2025921357
2026 (through Nov 16, 2026)344197

A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected. A permit is counted in the year of its issued date. Permits later withdrawn or expired are counted if they carry an issue date. The dataset names no contractor or license number, so permits are not linked to installers.

ZIP codes in Corona

ZIP codes with their own page where the utilities recorded Corona on at least 10% of the ZIP’s installs, through Aug 31, 2026.

928835,6245,650852
928824,0774,079523
928812,9452,947324
928802,8757,587913
928792,0652,069303
9287832633199
9287728280

SGIP battery storage projects in Corona

The SGIP report lists 630 battery storage projects with the city Corona, 342 with the status Paid ($2,675,441 in current incentive allocations, 5,948 kWh).

Status as publishedProjectsStorage kWhCurrent incentive
Paid3425,948$2,675,441
PBI in Process2582$180,205
Reserved657,636$2,130,799
Pending Reservation15298$356,820
Waitlist20315$518,362
Cancelled17714,765$6,927,237
RRF Rejected9122$16,750

Installers named on the most SGIP storage projects in Corona

InstallerProjectsPaid
Sunrun12173
SolarMax Renewable Energy Provider, Inc6436
Semper Solaris Construction Inc5243
Tesla4234
SunPower3018
Citadel Roofing and Solar230
Tesla Energy Operations (formerly SolarCity)1613
Infinity Energy, Inc156
V3 Electric1410
Precis Solar119

83 of the 630 projects name no installer with a page in this index, so they are counted above but not in this list.

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

All SGIP battery projects, and SGIP battery incentive money by county.

Municipal utility: City of Corona - (CA)

Corona has its own municipal utility, City of Corona - (CA). It reported 25 net-metered solar PV installations (20 residential) to EIA for 2025. Homes on a municipal utility are not in the PG&E, SCE and SDG&E interconnection records the counts above come from, so those counts leave this utility’s customers out.

From EIA’s Form EIA-861 2025 data files (downloaded Nov 16, 2026). EIA describes the net metering file this way: “The data contain cumulative installation count and capacity of generators that are net metered by technology, state, sector, and balancing authority.” Counts are utility-reported as of December 31, 2025, for each utility’s whole California service area. Unit is the capacity unit the utility reported, AC or DC; EIA’s utility rows are “reported as collected,” so DC and AC figures are not converted here. Blank cells are cells EIA printed as a period. EIA’s file notes: “All Technologies does not include batteries.”

At a glance

Residential solar installs
17,965
Last 24 months
2,184
Capacity
130.1 MW DC
Median system size
6.6 kW DC
With battery storage
17.3% all time; 73.4% last 24 months
Third-party owned
42.0% where reported
Ownership types recorded
PPA 4,809, lease 1,772, prepaid lease 28, other 368
Median battery size
13.5 kWh
Earliest install in data
Nov 2, 2001

Common questions

How many homes in Corona have solar?

17,965 residential solar systems in Corona were interconnected by PG&E, SCE or SDG&E through Aug 31, 2026, 2,184 of them in the last 24 months. Homes on municipal utilities are not included.

How many solar installers work in Corona?

220 installer names have at least one install interconnected in Corona in the last 24 months, and 960 appear in the full record.

How common are batteries with new solar in Corona?

17.3% of the solar installs interconnected in Corona include battery storage across all years, and 73.4% in the last 24 months (1,603 of 2,184).

How many solar installs in Corona are under NEM 3.0?

2,559 of the 17,965 residential solar installs in Corona (14.2% of the 17,965 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 78.2% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.