LUXOR ENERGY INC

How many solar installs has LUXOR ENERGY INC done in California, and which license number is on its installs?

LUXOR ENERGY INC has 610 residential solar installs interconnected in California, active in the records from 2023 through 2026 (Nov 14, 2023 to Aug 17, 2026), most of them in San Bernardino County (168), Los Angeles County (163) and Riverside County (136). CSLB lists license 1102673 (LUXOR ENERGY INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Mar 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
610
Last 24 months
452
Total capacity
4,458.9 kW DC
Median system size
6.8 kW DC
With battery storage
60.8% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 79.1% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
97.9% of 610 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
603 installs, latest Aug 17, 2026
Ownership types recorded
PPA 579, lease 2, other 16
Median battery size
9.7 kWh (347 installs list a capacity)
First install
Nov 14, 2023
Latest install
Aug 17, 2026
Counties
20
Utilities
SCE 531, PGE 69, SDGE 10
CSLB license
1102673

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2023 to 2026

YearInstalls interconnectedWith battery storage
2023100
2024348128
2025151136
2026 (through Aug 31, 2026)101101

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

603 of its 610 interconnected installs (98.9% of the 610 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 61.4% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Aug 17, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.071.1%1 (14.3%)
Net Billing Tariff60398.9%364 (61.4%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 597 of LUXOR ENERGY INC’s installs the utility recorded a third-party ownership type: PPA 579, lease 2, prepaid lease 0, other 16. Across all installers, 40 residential systems list a third-party owner name that matches LUXOR ENERGY INC exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Everbright400
GoodLeap LLC107
Luxor Energy39
LightReach15
Mosaic13

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 442 of LUXOR ENERGY INC’s 452 installs name a module maker in the “Generator Manufacturer” fields, and most of those (232, 52.5%) used modules recorded as Qcells.

In the last 24 months, 452 of LUXOR ENERGY INC’s 452 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (222, 49.1%) used inverters recorded as SolarEdge.

In the last 24 months, 344 of LUXOR ENERGY INC’s 452 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (181, 52.6%) used batteries recorded as SolarEdge.

356 of 365 battery-paired PG&E and SCE installs (97.5%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells232336
LONGi8086
JinkoSolar7474
REC3271
Q Cell16not in top list
Inverter makerSolarEdge222258
Enphase160273
Tesla8387
ABB88
Power-One44
Battery makerSolarEdge181190
Tesla9494
Enphase6972
Enpahse11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 600 of 610 installs, inverters on 610. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1102673LUXOR ENERGY INC (Corporation)CLEARC-10 Electrical ContractorMar 20, 2023Mar 31, 2027610

License numbers are the ones the utilities recorded on the interconnection applications (610 of 610 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1102673. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list LUXOR ENERGY INC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20242025Total
unincorporated San Diego County1102673213

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
San Bernardino168
Los Angeles163
Riverside136
Orange31
Tulare19
Fresno15
Kern15
Kings13
Alameda10
San Diego9
Contra Costa7
Merced6
Monterey4
Inyo3
Madera3
San Joaquin2
Solano2
Stanislaus2
Santa Clara1
Santa Cruz1

Top cities

CityInstalls
Corona32
Lancaster27
Moreno Valley25
Palmdale23
Lake Elsinore18
Riverside18
Apple Valley17
Ontario16
Alta Loma15
Fontana15
San Bernardino15
Rancho Cucamonga13
Victorville13
Hesperia10
Hemet9

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
LUXOR ENERGY INC600
Luxor Energy10

Common questions

Where does LUXOR ENERGY INC install solar?

Its installs are spread across 20 counties. The most are in San Bernardino County (168 installs), followed by Los Angeles County (163).

How often does LUXOR ENERGY INC install batteries with solar?

60.8% of its interconnected solar installs include battery storage across all years, and 79.1% in the last 24 months (353 of 446). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many LUXOR ENERGY INC installs are under NEM 3.0 (the Net Billing Tariff)?

603 of its 610 interconnected installs (98.9% of the 610 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 61.4% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.