Unlimited Energy

How many solar installs has Unlimited Energy done in California, and which license number is on its installs?

Unlimited Energy has 454 residential solar installs interconnected in California, active in the records from 2001 through 2016 (Apr 25, 2001 to Oct 27, 2016), most of them in Fresno County (266), Tulare County (62) and Madera County (50). The license number recorded on most of its installs, 545828, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
454
Last 24 months
0
Total capacity
2,380.3 kW DC
Median system size
4.7 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
2.7% of 403 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 11
First install
Apr 25, 2001
Latest install
Oct 27, 2016
Counties
13
Utilities
PGE 384, SCE 70
CSLB license
545828

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2001 to 2026

YearInstalls interconnectedWith battery storage
200110
2002140
2003280
2004480
2005380
2006640
2007890
2008590
2009400
2010320
201170
201250
201320
201470
2015180
201620
201700
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 454 interconnected installs with a tariff recorded (454) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.0454100.0%not counted
NEM 2.000.0%0
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 11 of Unlimited Energy’s installs the utility recorded a third-party ownership type: PPA 11, lease 0, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Unlimited Energy exactly.

Third-party owner named on its installsInstalls
Tier 1 Solar8
Tier 1 Solar Power3

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 372 of Unlimited Energy’s 454 installs name a module maker in the “Generator Manufacturer” fields, and most of those (197, 53.0%) used modules recorded as SolarWorld.

Across all years, 454 of Unlimited Energy’s 454 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (306, 67.4%) used inverters recorded as SMA.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSolarWorld0197
Shell Solar089
Sharp036
Siemens Solar Industries026
SunPower06
Inverter makerSMA0306
PV Powered084
Xantrex Technology Inc.022
Advanced Energy, Inc.017
APsystems (Altenergy Power System)015

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 372 of 454 installs, inverters on 454. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
545828Not found in the CSLB License Master file pulled Nov 4, 202678

License numbers are the ones the utilities recorded on the interconnection applications (85 of 454 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Counties

CountyInstalls
Fresno266
Tulare62
Madera50
Kern26
Kings23
Merced10
Mariposa5
San Luis Obispo5
Marin2
Santa Barbara2
Los Angeles1
Monterey1
San Joaquin1

Top cities

CityInstalls
Fresno129
Clovis89
Madera39
Visalia25
Bakersfield24
Hanford13
Sanger13
Lemoore10
Lindsay10
Coarsegold8
Tulare8
Merced6
Squaw Valley6
Exeter5
Dinuba4

Names as recorded by the utilities

The utilities recorded this installer under 13 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Unlimited Energy266
Unlimited Energy, Inc.82
UNLIMITED ENERGY57
Unlimited Energy, Inc13
Unlimited Energy Inc11
Unlimited Energy Inc.11
Unlimited Energy LLC5
UNLIMITED ENERGY LLC3
Unlimited Energy, LLC2
Unlimited Energy , Inc.1
Unlimited Energy inc.1
Unlimited Energy INC.1
Unlimited Energy, INC1

Common questions

Where does Unlimited Energy install solar?

Its installs are spread across 13 counties. The most are in Fresno County (266 installs), followed by Tulare County (62).

How often does Unlimited Energy install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many Unlimited Energy installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 454 interconnected installs with a tariff recorded (454) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.