McCormack Roofing

How many solar installs has McCormack Roofing done in California, and which license number is on its installs?

McCormack Roofing has 54 residential solar installs interconnected in California, active in the records from 2009 through 2026 (Oct 20, 2009 to Mar 13, 2026), most of them in Orange County (30), Los Angeles County (13) and San Bernardino County (4). CSLB lists license 643700 (MCCORMACK ROOFING & SOLAR INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-39, C-46, expires Jun 30, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
54
Last 24 months
7
Total capacity
352.4 kW DC
Median system size
5.6 kW DC
With battery storage
0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
Third-party owned
0.0% of 42 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
5 installs, latest Mar 13, 2026
Ownership types recorded
none recorded
First install
Oct 20, 2009
Latest install
Mar 13, 2026
Counties
5
Utilities
SCE 38, SDGE 16
CSLB license
643700

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2009 to 2026

YearInstalls interconnectedWith battery storage
200910
201030
201150
201230
2013110
2014110
201540
201600
201700
201800
201900
202000
202100
202200
202370
202430
202550
2026 (through Aug 31, 2026)10

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

5 of its 54 interconnected installs (9.3% of the 54 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Mar 13, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.03870.4%not counted
NEM 2.01120.4%not recorded
Net Billing Tariff59.3%not recorded

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on McCormack Roofing’s installs. No residential system in the file lists a third-party owner name that matches McCormack Roofing exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 6 of McCormack Roofing’s 7 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (2, 33.3%) used modules recorded as HDHYUNDAIENERGYSOLUTIONSCO.,LTD..

In the last 24 months, 7 of McCormack Roofing’s 7 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (5, 71.4%) used inverters recorded as Tesla.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerHDHYUNDAIENERGYSOLUTIONSCO.,LTD.22
UnitedRenewableEnergyCo.,Ltd.29
Solaria11
Tesla12
Inverter makerTesla56
Enphase120
PointGuardEnergyInc.11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 14 of 54 installs, inverters on 54. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
643700MCCORMACK ROOFING & SOLAR INC (Corporation)CLEARB General Building Contractor; C-39 Roofing Contractor; C-46 Solar ContractorApr 30, 1992Jun 30, 202853

License numbers are the ones the utilities recorded on the interconnection applications (53 of 54 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 643700. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Orange30
Los Angeles13
San Bernardino4
San Diego4
Riverside3

Top cities

CityInstalls
Laguna Hills4
Mission Viejo4
Dana Point3
Fullerton3
Corona2
Downey2
Huntington Beach2
Laguna Niguel2
Los Alamitos2
Pomona2
San Clemente2
San Juan Capo2
Torrance2
Trabuco Canyon2
Cerritos1

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
McCormack Roofing32
MCCORMACK ROOFING21
McCormack Roofing,1

Common questions

Where does McCormack Roofing install solar?

Its installs are spread across 5 counties. The most are in Orange County (30 installs), followed by Los Angeles County (13).

How often does McCormack Roofing install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many McCormack Roofing installs are under NEM 3.0 (the Net Billing Tariff)?

5 of its 54 interconnected installs (9.3% of the 54 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.