Wave Electric Energy

How many solar installs has Wave Electric Energy done in California, and which license number is on its installs?

Wave Electric Energy has 401 residential solar installs interconnected in California, active in the records from 2020 through 2026 (May 7, 2020 to Aug 13, 2026), most of them in San Diego County (385) and Orange County (16). CSLB lists license 1059958 (WAVE ELECTRIC ENERGY LLC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires May 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
401
Last 24 months
47
Total capacity
2,734.9 kW DC
Median system size
6.4 kW DC
With battery storage
not recorded (SDG&E files batteries as separate projects, not on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
Third-party owned
0.0% of 401 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
53 installs, latest Aug 13, 2026
Ownership types recorded
none recorded
First install
May 7, 2020
Latest install
Aug 13, 2026
Counties
2
Utilities
SDGE 401
CSLB license
1059958

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2020 to 2026

YearInstalls interconnectedWith battery storage
2020390
2021960
20221360
2023700
2024190
2025270
2026 (through Aug 31, 2026)140

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

53 of its 401 interconnected installs (13.2% of the 401 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Aug 13, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.034886.8%not recorded
Net Billing Tariff5313.2%not recorded

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Wave Electric Energy’s installs. No residential system in the file lists a third-party owner name that matches Wave Electric Energy exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 46 of Wave Electric Energy’s 47 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (22, 47.8%) used modules recorded as HDHYUNDAIENERGYSOLUTIONSCO.,LTD..

In the last 24 months, 47 of Wave Electric Energy’s 47 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (34, 72.3%) used inverters recorded as Tesla.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerHDHYUNDAIENERGYSOLUTIONSCO.,LTD.2222
REC21115
Canadian Solar1not in top list
JA Solar1not in top list
Qcells125
Inverter makerTesla3435
Enphase13365
SMA12

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 383 of 401 installs, inverters on 401. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Wave Electric Energy as developer on 0 battery storage projects and as installer on 1 (0 name it as both), 1 projects in all with 40 kWh of storage. 1 have the status Paid, with $26,907 in current incentive allocations. Applications were received from Oct 27, 2022 to Oct 27, 2022.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid140$26,907

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency140$26,9071$26,907

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1059958WAVE ELECTRIC ENERGY LLC (Limited Liability)CLEARC-10 Electrical ContractorNov 4, 2019May 31, 2028401

License numbers are the ones the utilities recorded on the interconnection applications (401 of 401 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1059958. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Wave Electric Energy’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2020202120222023202420252026Total
unincorporated San Diego County1059958201925338115121

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
San Diego385
Orange16

Top cities

CityInstalls
San Diego139
El Cajon40
Chula Vista32
Alpine30
Lakeside25
La Mesa20
Santee16
Ramona15
Spring Valley11
Poway10
La Jolla8
Escondido7
Oceanside6
San Marcos6
Carlsbad5

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Wave Electric Energy401

Common questions

Where does Wave Electric Energy install solar?

Its installs are spread across 2 counties. The most are in San Diego County (385 installs), followed by Orange County (16).

How often does Wave Electric Energy install batteries with solar?

Battery storage is not recorded on its interconnected solar installs: SDG&E files a battery as its own project record, not on the solar record.

How many Wave Electric Energy installs are under NEM 3.0 (the Net Billing Tariff)?

53 of its 401 interconnected installs (13.2% of the 401 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.