Solar installers in Ramona, California
Most installs here are in Orange County.
Who installs the most solar in Ramona?
Ranked by interconnected installs in the last 24 months (Sep 2024 through Aug 2026), the top three installers in Ramona are Sunrun (83), Semper Solaris Construction Inc (35) and Baker Electric, Inc. (34). They account for 152 of the 475 residential solar installs interconnected there in that window.
In all, 6,288 homes in Ramona have residential solar interconnected by PG&E, SCE or SDG&E through Aug 31, 2026. These are counts of connected systems, not a rating of any installer.
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installers ranked by interconnected installs, last 24 months
Sep 2024 through Aug 2026. Top 25 of 81 installers with installs in this window. 20 installs in the window were self-installed or had no installer recorded.
| 1 | Sunrun | 83 | 532 |
| 2 | Semper Solaris Construction Inc | 35 | 351 |
| 3 | Baker Electric, Inc. | 34 | 667 |
| 4 | Bright Planet Solar | 33 | 186 |
| 5 | GAF Energy | 27 | 27 |
| 6 | Solar Universe San Marcos | 24 | 52 |
| 7 | Elite Solar | 16 | 82 |
| 8 | Freedom Solar Co | 16 | 67 |
| 9 | Stellar Solar | 14 | 123 |
| 10 | Solartech | 13 | 65 |
| 11 | Empower Electric Solar | 11 | 11 |
| 12 | Tesla Energy Operations (formerly SolarCity) | 11 | 386 |
| 13 | PALOMAR SOLAR LTD | 6 | 81 |
| 14 | Alltech Solar | 5 | 8 |
| 15 | Aloha Solar Power | 5 | 12 |
| 16 | BETTER EARTH ELECTRIC INC | 5 | 11 |
| 17 | EXO Energy | 5 | 52 |
| 18 | PEAK ENERGY GROUP | 5 | 5 |
| 19 | Sungenia Solar Solutions | 5 | 17 |
| 20 | ALIVE Industries, Inc. | 4 | 14 |
| 21 | Current Home | 4 | 42 |
| 22 | LGCY INSTALLATION SERVICES LLC DBA LGCY ELECTRIC | 4 | 6 |
| 23 | Simms Solar Electric Inc. | 4 | 118 |
| 24 | Sunline Energy Inc. | 4 | 50 |
| 25 | Blalock electric | 3 | 27 |
Most installs, all time
| 1 | Baker Electric, Inc. | 667 | 667 |
| 2 | Sunrun | 532 | 532 |
| 3 | Vivint Solar Developer, LLC | 432 | 432 |
| 4 | Tesla Energy Operations (formerly SolarCity) | 386 | 386 |
| 5 | Semper Solaris Construction Inc | 351 | 351 |
| 6 | Bright Planet Solar | 186 | 186 |
| 7 | Sullivan Solar Power | 132 | 132 |
| 8 | Stellar Solar | 123 | 123 |
| 9 | Simms Solar Electric Inc. | 118 | 118 |
| 10 | Solar West Electric, Inc. | 91 | 91 |
Installs by year
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2022 | 596 | 0 |
| 2023 | 532 | 0 |
| 2024 | 226 | 0 |
| 2025 | 266 | 0 |
| 2026 (through Aug 31, 2026) | 147 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Under the Net Billing Tariff (NEM 3.0)
574 of the 6,288 residential solar installs in Ramona (9.1% of the 6,288 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest was approved Aug 26, 2026. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023, under CPUC Decision D.22-12-056.
Installers ranked by Net Billing Tariff installs in Ramona
| 1 | Sunrun | 124 | 0 | not recorded |
| 2 | Semper Solaris Construction Inc | 51 | 0 | not recorded |
| 3 | Bright Planet Solar | 42 | 0 | not recorded |
| 4 | Baker Electric, Inc. | 32 | 0 | not recorded |
| 5 | GAF Energy | 27 | 0 | not recorded |
| 6 | Solar Universe San Marcos | 24 | 0 | not recorded |
| 7 | Freedom Solar Co | 17 | 0 | not recorded |
| 8 | Elite Solar | 16 | 0 | not recorded |
| 9 | Stellar Solar | 16 | 0 | not recorded |
| 10 | Tesla Energy Operations (formerly SolarCity) | 15 | 0 | not recorded |
| 11 | Solartech | 14 | 0 | not recorded |
| 12 | Empower Electric Solar | 11 | 0 | not recorded |
| 13 | SunPower | 9 | 0 | not recorded |
| 14 | EXO Energy | 8 | 0 | not recorded |
| 15 | BETTER EARTH ELECTRIC INC | 7 | 0 | not recorded |
Top 15, all Net Billing Tariff installs through Aug 31, 2026. Counts of connected systems, not a rating.
Equipment recorded
In the last 24 months, 374 of Ramona’s 475 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (122, 32.6%) used modules recorded as Qcells.
In the last 24 months, 475 of Ramona’s 475 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (278, 58.5%) used inverters recorded as Tesla.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Qcells | 122 | 840 |
| Canadian Solar | 49 | 305 | |
| LONGi | 47 | not in top list | |
| Silfab | 35 | 198 | |
| JA Solar | 28 | not in top list | |
| Inverter maker | Tesla | 278 | 329 |
| Enphase | 150 | 2,195 | |
| SolarEdge | 81 | 2,058 | |
| SMA | 8 | 645 | |
| ABB | 6 | 209 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 5,215 of 6,288 installs, inverters on 5,939. See the methodology and the equipment index.
ZIP codes in Ramona
ZIP codes with their own page where the utilities recorded Ramona on at least 10% of the ZIP’s installs, through Aug 31, 2026.
| 92065 | 6,288 | 6,288 | 475 |
SGIP battery storage projects in Ramona
The SGIP report lists 719 battery storage projects with the city Ramona, 469 with the status Paid ($9,455,308 in current incentive allocations, 12,078 kWh).
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 469 | 12,078 | $9,455,308 |
| PBI in Process | 1 | 1,469 | $1,387,400 |
| Reserved | 25 | 543 | $450,787 |
| Pending Reservation | 2 | 37 | $5,486 |
| Waitlist | 3 | 55 | $96,140 |
| Cancelled | 217 | 5,674 | $4,290,825 |
| RRF Rejected | 2 | 26 | $3,960 |
Installers named on the most SGIP storage projects in Ramona
| Installer | Projects | Paid |
|---|---|---|
| Semper Solaris Construction Inc | 262 | 190 |
| Sunrun | 29 | 13 |
| Solar Watt Solutions | 28 | 8 |
| Solare Energy, Inc | 21 | 18 |
| Sullivan Solar Power | 21 | 18 |
| Infinity Energy, Inc | 15 | 6 |
| APOLLO HOME POWER LLC | 12 | 1 |
| ALIVE Industries, Inc. | 11 | 7 |
| Home Energy Systems, Inc. | 11 | 9 |
| TMAG INDUSTRIES INC | 9 | 8 |
186 of the 719 projects name no installer with a page in this index, so they are counted above but not in this list.
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
All SGIP battery projects, and SGIP battery incentive money by county.
At a glance
- Residential solar installs
- 6,288
- Last 24 months
- 475
- Capacity
- 50.8 MW DC
- Median system size
- 7.3 kW DC
- With battery storage
- not recorded (SDG&E files batteries as separate projects, not on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
- Third-party owned
- 29.8% where reported
- Ownership types recorded
- PPA 1,163, lease 183, prepaid lease 10, other 116
- Earliest install in data
- Mar 30, 1999
Common questions
How many homes in Ramona have solar?
6,288 residential solar systems in Ramona were interconnected by PG&E, SCE or SDG&E through Aug 31, 2026, 475 of them in the last 24 months. Homes on municipal utilities are not included.
How many solar installers work in Ramona?
81 installer names have at least one install interconnected in Ramona in the last 24 months, and 515 appear in the full record.
How common are batteries with new solar in Ramona?
Battery storage is not recorded on the solar installs interconnected in Ramona: SDG&E files a battery as its own project record, not on the solar record.
How many solar installs in Ramona are under NEM 3.0?
574 of the 6,288 residential solar installs in Ramona (9.1% of the 6,288 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.