Alternative Energy Applications, Inc.
How many solar installs has Alternative Energy Applications, Inc. done in California, and which license number is on its installs?
Alternative Energy Applications, Inc. has 340 residential solar installs interconnected in California, active in the records from 2014 through 2026 (Feb 25, 2014 to Aug 10, 2026), most of them in San Diego County (334), Orange County (5) and Riverside County (1). CSLB lists license 882034 (MACKAIG ELECTRIC INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Jan 31, 2027.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
The installs credited to Alternative Energy Applications, Inc. here carry more than one CSLB license number: 882034 on 146 (CSLB holder MACKAIG ELECTRIC INC, Lakeside), 1095700 on 85 (CSLB holder Sole owner license (name not shown)) and 985761 on 72 (CSLB holder ALTERNATIVE ENERGY APPLICATIONS INC, San Diego), in the License Master file pulled Nov 4, 2026. They are grouped under one installer by the name written on the applications; the records do not say whether these numbers belong to the same legal entity.
- Interconnected installs
- 340
- Last 24 months
- 61
- Total capacity
- 2,080.7 kW DC
- Median system size
- 5.2 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
- Third-party owned
- 0.0% of 324 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 53 installs, latest Aug 10, 2026
- Ownership types recorded
- none recorded
- First install
- Feb 25, 2014
- Latest install
- Aug 10, 2026
- Counties
- 3
- Utilities
- SDGE 339, SCE 1
- CSLB license
- 882034, 1095700, 985761
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2014 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2014 | 12 | 0 |
| 2015 | 14 | 0 |
| 2016 | 25 | 0 |
| 2017 | 17 | 0 |
| 2018 | 24 | 0 |
| 2019 | 24 | 0 |
| 2020 | 31 | 0 |
| 2021 | 31 | 0 |
| 2022 | 37 | 0 |
| 2023 | 54 | 0 |
| 2024 | 32 | 0 |
| 2025 | 25 | 0 |
| 2026 (through Aug 31, 2026) | 14 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
53 of its 340 interconnected installs (15.6% of the 340 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Aug 10, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 42 | 12.4% | not counted |
| NEM 2.0 | 245 | 72.1% | 0 (0.0%) |
| Net Billing Tariff | 53 | 15.6% | not recorded |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Alternative Energy Applications, Inc.’s installs. No residential system in the file lists a third-party owner name that matches Alternative Energy Applications, Inc. exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 61 of Alternative Energy Applications, Inc.’s 61 installs name a module maker in the “Generator Manufacturer” fields, and most of those (56, 91.8%) used modules recorded as Qcells.
In the last 24 months, 61 of Alternative Energy Applications, Inc.’s 61 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (55, 90.2%) used inverters recorded as Enphase.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Qcells | 56 | 156 |
| LONGi | 4 | 5 | |
| Aptos Solar | 1 | not in top list | |
| Inverter maker | Enphase | 55 | 248 |
| SolarEdge | 6 | 54 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 337 of 340 installs, inverters on 340. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 882034 | MACKAIG ELECTRIC INC (Corporation) | CLEAR | C-10 Electrical Contractor | Aug 4, 2006 | Jan 31, 2027 | 146 |
| 1095700 | Sole owner license (name not shown) | CLEAR | B General Building Contractor | Aug 23, 2022 | Aug 31, 2028 | 85 |
| 985761 | ALTERNATIVE ENERGY APPLICATIONS INC (Corporation) | CLEAR | A General Engineering Contractor | Jul 31, 2013 | Jul 31, 2027 | 72 |
License numbers are the ones the utilities recorded on the interconnection applications (303 of 340 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for licenses 882034, 1095700, 985761. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Counties
Top cities
| City | Installs |
|---|---|
| San Diego | 91 |
| El Cajon | 71 |
| Alpine | 42 |
| Santee | 39 |
| Lakeside | 24 |
| Spring Valley | 10 |
| Coronado | 9 |
| La Mesa | 8 |
| Encinitas | 7 |
| Descanso | 5 |
| La Jolla | 5 |
| Ramona | 3 |
| Rancho Santa Fe | 3 |
| Borrego Springs | 2 |
| Carlsbad | 2 |
Names as recorded by the utilities
The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Alternative Energy Applications, Inc. | 339 |
| ALTERNATIVE ENERGY APPLICATIONS INC | 1 |
Common questions
Where does Alternative Energy Applications, Inc. install solar?
Its installs are spread across 3 counties. The most are in San Diego County (334 installs), followed by Orange County (5).
How often does Alternative Energy Applications, Inc. install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many Alternative Energy Applications, Inc. installs are under NEM 3.0 (the Net Billing Tariff)?
53 of its 340 interconnected installs (15.6% of the 340 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.