Empowered Energy Solutions, Inc.

How many solar installs has Empowered Energy Solutions, Inc. done in California, and which license number is on its installs?

Empowered Energy Solutions, Inc. has 175 residential solar installs interconnected in California, active in the records from 2009 through 2019 (Dec 23, 2009 to Jan 31, 2019), most of them in San Diego County (171) and Orange County (4). The utilities did not record a CSLB license number on enough of these installs to look one up.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
175
Last 24 months
0
Total capacity
1,117.5 kW DC
Median system size
5.7 kW DC
With battery storage
not recorded (SDG&E files batteries as separate projects, not on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 62 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Dec 23, 2009
Latest install
Jan 31, 2019
Counties
2
Utilities
SDGE 175
CSLB license
none reported

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2009 to 2026

YearInstalls interconnectedWith battery storage
200910
201070
201170
2012190
2013240
2014420
2015450
2016250
201700
201830
201920
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 175 interconnected installs with a tariff recorded (175) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.016996.6%not counted
NEM 2.063.4%not recorded
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Empowered Energy Solutions, Inc.’s installs. No residential system in the file lists a third-party owner name that matches Empowered Energy Solutions, Inc. exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 171 of Empowered Energy Solutions, Inc.’s 175 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (74, 43.3%) used modules recorded as Qcells.

Across all years, 153 of Empowered Energy Solutions, Inc.’s 175 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (78, 51.0%) used inverters recorded as SolarEdge.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells074
Suniva028
LG024
SunPower023
SolarWorld09
Inverter makerSolarEdge078
Enphase051
Power-One012
SMA09
PV Powered01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 171 of 175 installs, inverters on 153. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Empowered Energy Solutions, Inc. as developer on 0 battery storage projects and as installer on 2 (0 name it as both), 2 projects in all with 118 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from Feb 23, 2016 to May 1, 2017.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Cancelled2118$104,998

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Large-Scale Storage159$29,6450$0
Not stated159$75,3530$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

The utilities did not record a license number for enough of these installs to look one up.

License numbers are the ones the utilities recorded on the interconnection applications (8 of 175 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it.

Counties

CountyInstalls
San Diego171
Orange4

Top cities

CityInstalls
San Diego40
La Mesa22
El Cajon13
Escondido13
Encinitas12
Carlsbad10
Vista8
San Marcos7
Oceanside6
Spring Valley6
Chula Vista5
Lakeside4
Poway4
Ramona4
Del Mar3

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Empowered Energy Solutions, Inc.175

Common questions

Where does Empowered Energy Solutions, Inc. install solar?

Its installs are spread across 2 counties. The most are in San Diego County (171 installs), followed by Orange County (4).

How often does Empowered Energy Solutions, Inc. install batteries with solar?

Battery storage is not recorded on its interconnected solar installs: SDG&E files a battery as its own project record, not on the solar record.

How many Empowered Energy Solutions, Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 175 interconnected installs with a tariff recorded (175) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.