Homelink Solar

How many solar installs has Homelink Solar done in California, and which license number is on its installs?

Homelink Solar has 73 residential solar installs interconnected in California, active in the records from 2024 through 2026 (Jul 17, 2024 to Aug 31, 2026), most of them in San Diego County (29), Orange County (9) and Sonoma County (8). CSLB lists license 1117534 (HOMELINK SOLAR) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Mar 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
73
Last 24 months
72
Total capacity
555 kW DC
Median system size
6.8 kW DC
With battery storage
97.1% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 97.1% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
5.6% of 72 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
69 installs, latest Aug 31, 2026
Ownership types recorded
PPA 1, lease 3
Median battery size
13.5 kWh (27 installs list a capacity)
First install
Jul 17, 2024
Latest install
Aug 31, 2026
Counties
15
Utilities
SDGE 38, PGE 25, SCE 10
CSLB license
1117534

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2024 to 2026

YearInstalls interconnectedWith battery storage
202460
20253716
2026 (through Aug 31, 2026)3018

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

69 of its 73 interconnected installs (95.8% of the 72 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Aug 31, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.011.4%not counted
NEM 2.022.8%1 (50.0%)
Net Billing Tariff6995.8%32 (100.0%)
Not recorded1

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 4 of Homelink Solar’s installs the utility recorded a third-party ownership type: PPA 1, lease 3, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Homelink Solar exactly.

Third-party owner named on its installsInstalls
Tyron Salise4

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 71 of Homelink Solar’s 72 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (28, 39.4%) used modules recorded as Qcells.

In the last 24 months, 71 of Homelink Solar’s 72 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (57, 80.3%) used inverters recorded as Tesla.

In the last 24 months, 31 of Homelink Solar’s 72 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (25, 80.6%) used batteries recorded as Tesla.

31 of 34 battery-paired PG&E and SCE installs (91.2%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells2829
Hyundai1515
HDHYUNDAIENERGYSOLUTIONSCO.,LTD.1212
SEGSolarInc.44
LONGi33
Inverter makerTesla5757
Enphase1314
FranklinWH33
ABB22
Battery makerTesla2525
Enphase33
FranklinWH33

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 72 of 73 installs, inverters on 72. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Homelink Solar as developer on 0 battery storage projects and as installer on 29 (0 name it as both), 29 projects in all with 584 kWh of storage. 4 have the status Paid, with $77,439 in current incentive allocations. Applications were received from Feb 18, 2025 to Jul 29, 2026.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid4112$77,439
Reserved7113$142,478
Pending Reservation579$134,795
Waitlist7146$227,821
Cancelled6134$93,229

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Residential Solar and Storage Equity - AB 209 Non-POU16265$479,9260$0
Equity Resiliency12292$192,2974$77,439
Small Residential Storage127$3,5400$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1117534HOMELINK SOLAR (Limited Liability)CLEAR, Pending IFSC-10 Electrical ContractorMar 7, 2024Mar 31, 202872

License numbers are the ones the utilities recorded on the interconnection applications (72 of 73 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The License Master file lists a pending suspension date of Nov 29, 2026 for license 1117534. A pending date is CSLB’s scheduled action if the underlying requirement is not met; it is not a finding of wrongdoing.

What a disciplinary bond is: CSLB’s Bond Basics page says that when a license has been revoked, or in some instances suspended, for a violation of the Contractors State License Law, the contractor must file a disciplinary bond with the Registrar to reinstate, reissue or reapply for a license, and that the bond must stay on file for at least two years (CSLB Bond Basics). The file gives one disciplinary bond entry per license and does not say which of those circumstances applied, what the case was about or how it ended. CSLB’s license detail page shows any public disciplinary action.

Local solar permits naming its license

Solar permits in city and county open data that list Homelink Solar’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20252026Total
City and County of San Francisco1117534011
unincorporated San Diego County1117534123

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
San Diego29
Orange9
Sonoma8
Los Angeles5
Marin5
San Bernardino4
Solano3
El Dorado2
Merced2
Butte1
Contra Costa1
Kern1
Riverside1
San Francisco1
San Luis Obispo1

Top cities

CityInstalls
Escondido7
San Diego6
Chula Vista5
Santa Rosa5
Apple Valley4
El Cajon4
San Clemente4
San Rafael4
Mission Viejo2
Oceanside2
Palmdale2
Petaluma2
Pomona2
Winton2
Bakersfield1

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Homelink Solar38
HOMELINK SOLAR35

Common questions

Where does Homelink Solar install solar?

Its installs are spread across 15 counties. The most are in San Diego County (29 installs), followed by Orange County (9).

How often does Homelink Solar install batteries with solar?

97.1% of its interconnected solar installs include battery storage across all years, and 97.1% in the last 24 months (34 of 35). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Homelink Solar installs are under NEM 3.0 (the Net Billing Tariff)?

69 of its 73 interconnected installs (95.8% of the 72 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.