How many solar installs has Optimum Solar Power done in California, and which license number is on its installs?

Optimum Solar Power has 36 residential solar installs interconnected in California, active in the records from 2017 through 2026 (Jun 8, 2017 to Apr 23, 2026), most of them in Riverside County (17), Orange County (8) and Los Angeles County (5). CSLB lists license 1024381 (OPTIMUM SOLAR POWER INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications A, C-10, C-46, expires Jan 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
36
Last 24 months
3
Total capacity
348.7 kW DC
Median system size
8.6 kW DC
With battery storage
8.3% all time; 100.0% last 24 months
Third-party owned
0.0% of 36 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
3 installs, latest Apr 23, 2026
Ownership types recorded
none recorded
Median battery size
20.5 kWh (3 installs list a capacity)
First install
Jun 8, 2017
Latest install
Apr 23, 2026
Counties
5
Utilities
SCE 34, PGE 2
CSLB license
1024381

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2017 to 2026

YearInstalls interconnectedWith battery storage
201760
2018120
201940
202000
202130
202250
202330
202400
202522
2026 (through Aug 31, 2026)11

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

3 of its 36 interconnected installs (8.3% of the 36 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Apr 23, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.025.6%not counted
NEM 2.03186.1%0 (0.0%)
Net Billing Tariff38.3%3 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Optimum Solar Power’s installs. No residential system in the file lists a third-party owner name that matches Optimum Solar Power exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 3 of Optimum Solar Power’s 3 installs name a module maker in the “Generator Manufacturer” fields, and most of those (2, 66.7%) used modules recorded as Deye.

In the last 24 months, 3 of Optimum Solar Power’s 3 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (2, 66.7%) used inverters recorded as Sol-Ark.

0 of 3 battery-paired PG&E and SCE installs (0.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerDeye2not in top list
Trina Solar2not in top list
Canadian Solar14
GoodWe Technologies Co., Ltd.1not in top list
Inverter makerSol-Ark22
GoodWe Technologies Co., Ltd.11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 35 of 36 installs, inverters on 36. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1024381OPTIMUM SOLAR POWER INC (Corporation)CLEARA General Engineering Contractor; C-10 Electrical Contractor; C-46 Solar ContractorMar 7, 2017Jan 31, 202835

License numbers are the ones the utilities recorded on the interconnection applications (35 of 36 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1024381. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Optimum Solar Power’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20212025Total
unincorporated San Diego County1024381112

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
Riverside17
Orange8
Los Angeles5
San Bernardino4
Fresno2

Top cities

CityInstalls
Corona8
Riverside3
Highland2
Perris2
Alhambra1
Aliso Viejo1
Alta Loma1
Buena Park1
Clovis1
Fountain Valley1
Fresno1
Garden Grove1
Glendora1
La Verne1
Lake Elsinore1

Names as recorded by the utilities

The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
OPTIMUM SOLAR POWER INC24
OPTIMUM SOLAR POWER6
Optimum Solar Power4
optimum solar power1
optimum solar power inc1

Common questions

Where does Optimum Solar Power install solar?

Its installs are spread across 5 counties. The most are in Riverside County (17 installs), followed by Orange County (8).

How often does Optimum Solar Power install batteries with solar?

8.3% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (3 of 3).

How many Optimum Solar Power installs are under NEM 3.0 (the Net Billing Tariff)?

3 of its 36 interconnected installs (8.3% of the 36 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.