SEPAC ENERGY SYSTEMS INC

How many solar installs has SEPAC ENERGY SYSTEMS INC done in California, and which license number is on its installs?

SEPAC ENERGY SYSTEMS INC has 103 residential solar installs interconnected in California, active in the records from 2013 through 2025 (Jan 16, 2013 to Jul 23, 2025), most of them in Contra Costa County (15), El Dorado County (12) and Sonoma County (12). The license number recorded on most of its installs, 952597, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
103
Last 24 months
6
Total capacity
827.7 kW DC
Median system size
7.5 kW DC
With battery storage
17.5% all time; 66.7% last 24 months
Third-party owned
6.8% of 103 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
14 installs, latest Dec 17, 2024
Ownership types recorded
PPA 7
Median battery size
10 kWh (5 installs list a capacity)
First install
Jan 16, 2013
Latest install
Jul 23, 2025
Counties
20
Utilities
PGE 103
CSLB license
952597

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2013 to 2026

YearInstalls interconnectedWith battery storage
201320
201410
201560
201660
201730
201820
201950
2020130
2021211
202292
2023213
20241111
202531
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

14 of its 103 interconnected installs (13.6% of the 103 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 78.6% of those include battery storage. The latest Net Billing Tariff install was approved Dec 17, 2024.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.01514.6%not counted
NEM 2.07471.8%7 (9.5%)
Net Billing Tariff1413.6%11 (78.6%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 7 of SEPAC ENERGY SYSTEMS INC’s installs the utility recorded a third-party ownership type: PPA 7, lease 0, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches SEPAC ENERGY SYSTEMS INC exactly.

Third-party owner named on its installsInstalls
Solrite4
Solrite/ Solnova2
Sunnova Energy Corporation1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 4 of SEPAC ENERGY SYSTEMS INC’s 6 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (2, 50.0%) used modules recorded as Mission Solar.

In the last 24 months, 6 of SEPAC ENERGY SYSTEMS INC’s 6 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (4, 66.7%) used inverters recorded as Enphase.

In the last 24 months, 2 of SEPAC ENERGY SYSTEMS INC’s 6 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (2, 100.0%) used batteries recorded as sonnen.

14 of 18 battery-paired PG&E and SCE installs (77.8%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerMission Solar28
Qcells220
Inverter makerEnphase438
Power Center22
sonnen29
SolarEdge160
Tesla1not in top list
Battery makersonnen28

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 99 of 103 installs, inverters on 103. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names SEPAC ENERGY SYSTEMS INC as developer on 12 battery storage projects and as installer on 10 (9 name it as both), 13 projects in all with 295 kWh of storage. 4 have the status Paid, with $28,147 in current incentive allocations. Applications were received from May 1, 2017 to Sep 20, 2024.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid478$28,147
Cancelled8198$44,146
RRF Rejected119$2,607

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage8154$23,0213$8,735
Large-Scale Storage3103$29,8600$0
Equity Resiliency119$19,4121$19,412
Not stated119$2,6070$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
952597Not found in the CSLB License Master file pulled Nov 4, 2026100

License numbers are the ones the utilities recorded on the interconnection applications (100 of 103 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Counties

CountyInstalls
Contra Costa15
El Dorado12
Sonoma12
Alameda11
Placer10
Solano9
San Joaquin7
Nevada5
Amador3
Marin3
Merced3
Santa Clara3
Sutter2
Yolo2
Butte1
Glenn1
Lake1
Stanislaus1
Tuolumne1
Yuba1

Top cities

CityInstalls
Rocklin6
Windsor6
Grass Valley5
Concord4
Oakland4
Brentwood3
Fairfield3
Pilot Hill3
Pleasanton3
Stockton3
Vacaville3
Acampo2
Lincoln2
Livingston2
Placerville2

Names as recorded by the utilities

The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SEPAC ENERGY SYSTEMS INC82
SePac Energy Systems Inc9
SePac Energy Systems7
SEPAC ENERGY SYSTEMS2
SePac Energy Systems, Inc.2
SePac Energy Systems, Inc1

Common questions

Where does SEPAC ENERGY SYSTEMS INC install solar?

Its installs are spread across 20 counties. The most are in Contra Costa County (15 installs), followed by El Dorado County (12).

How often does SEPAC ENERGY SYSTEMS INC install batteries with solar?

17.5% of its interconnected solar installs include battery storage across all years, and 66.7% in the last 24 months (4 of 6).

How many SEPAC ENERGY SYSTEMS INC installs are under NEM 3.0 (the Net Billing Tariff)?

14 of its 103 interconnected installs (13.6% of the 103 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 78.6% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.