SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION

How many solar installs has SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION done in California, and which license number is on its installs?

SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION has 204 residential solar installs interconnected in California, active in the records from 2019 through 2024 (Sep 16, 2019 to Aug 23, 2024), most of them in Los Angeles County (55), San Bernardino County (52) and Riverside County (45). The license number recorded on most of its installs, 1054677, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
204
Last 24 months
0
Total capacity
1,645.8 kW DC
Median system size
7.6 kW DC
With battery storage
2.5% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
2.0% of 204 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 3, lease 1
Median battery size
10.1 kWh (5 installs list a capacity)
First install
Sep 16, 2019
Latest install
Aug 23, 2024
Counties
10
Utilities
SCE 197, SDGE 6, PGE 1
CSLB license
1054677

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2019 to 2026

YearInstalls interconnectedWith battery storage
201930
202050
2021130
20221665
2023150
202420
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 204 interconnected installs with a tariff recorded (204) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.0204100.0%5 (2.5%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 4 of SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION’s installs the utility recorded a third-party ownership type: PPA 3, lease 1, prepaid lease 0, other 0. Across all installers, 5 residential systems list a third-party owner name that matches SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
SKY COUNTRY SOLAR4

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 155 of SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION’s 204 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (69, 44.5%) used modules recorded as Qcells.

Across all years, 204 of SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION’s 204 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (88, 43.1%) used inverters recorded as SolarEdge.

Across all years, 4 of SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION’s 204 installs name a battery maker in the “Generator Manufacturer” fields, and the most common maker (2, 50.0%) used batteries recorded as Enphase.

4 of 5 battery-paired PG&E and SCE installs (80.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells069
REC043
Silfab020
Panasonic07
LG06
Inverter makerSolarEdge088
Enphase079
SunPower025
Tesla06
LG02
Battery makerEnphase02
Generac02

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 155 of 204 installs, inverters on 204. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION as developer on 0 battery storage projects and as installer on 22 (0 name it as both), 22 projects in all with 287 kWh of storage. 9 have the status Paid, with $44,533 in current incentive allocations. Applications were received from Jul 20, 2021 to Sep 14, 2022.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid9117$44,533
Cancelled8101$16,767
RRF Rejected569$10,233

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage13151$22,9227$12,451
Equity Resiliency235$32,0822$32,082
Large-Scale Storage232$6,2960$0
Not stated569$10,2330$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1054677Not found in the CSLB License Master file pulled Nov 4, 2026201

License numbers are the ones the utilities recorded on the interconnection applications (204 of 204 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Local solar permits naming its license

Solar permits in city and county open data that list SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20212022Total
City and County of San Francisco1054677011
unincorporated San Diego County1054677628
unincorporated Marin County1054677202

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Los Angeles55
San Bernardino52
Riverside45
Orange37
Ventura5
Kern3
San Diego3
Santa Barbara2
Marin1
Tulare1

Top cities

CityInstalls
Fontana11
Victorville8
Santa Ana6
Apple Valley5
Corona5
Irvine5
Lancaster5
Whittier5
Covina4
Hemet4
Lake Elsinore4
Palm Desert4
Redlands4
San Bernardino4
Beaumont3

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION187
SKY COUNTRY SOLAR10
Sky Country Solar7

Common questions

Where does SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION install solar?

Its installs are spread across 10 counties. The most are in Los Angeles County (55 installs), followed by San Bernardino County (52).

How often does SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION install batteries with solar?

2.5% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many SKY COUNTRY SOLAR DBA SKY COUNTRY CONSTRUCTION installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 204 interconnected installs with a tariff recorded (204) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.