underline energy

How many solar installs has underline energy done in California, and which license number is on its installs?

underline energy has 326 residential solar installs interconnected in California, active in the records from 2016 through 2026 (May 5, 2016 to Jul 1, 2026), most of them in San Diego County (310) and Orange County (16). CSLB lists license 1015714 (UNDERLINE ENERGY CONCEPTS) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-20, C-39, expires Jul 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
326
Last 24 months
7
Total capacity
2,195.4 kW DC
Median system size
6.1 kW DC
With battery storage
not recorded (SDG&E files batteries as separate projects, not on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
Third-party owned
2.5% of 326 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
9 installs, latest Jul 1, 2026
Ownership types recorded
PPA 2, lease 3, prepaid lease 3
First install
May 5, 2016
Latest install
Jul 1, 2026
Counties
2
Utilities
SDGE 326
CSLB license
1015714

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2016 to 2026

YearInstalls interconnectedWith battery storage
2016250
2017130
2018330
2019430
2020460
2021220
2022460
2023760
2024190
202510
2026 (through Aug 31, 2026)20

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

9 of its 326 interconnected installs (2.8% of the 326 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Jul 1, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.061.8%not counted
NEM 2.031195.4%not recorded
Net Billing Tariff92.8%not recorded

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 8 of underline energy’s installs the utility recorded a third-party ownership type: PPA 2, lease 3, prepaid lease 3, other 0. No residential system in the file lists a third-party owner name that matches underline energy exactly.

Third-party owner named on its installsInstalls
sunrun2
underline concepts2
hdcap1
hdmcap1
kevin burt elec1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 7 of underline energy’s 7 installs name a module maker in the “Generator Manufacturer” fields, and most of those (6, 85.7%) used modules recorded as Silfab.

In the last 24 months, 7 of underline energy’s 7 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (3, 42.9%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSilfab6206
Aptos Solar1not in top list
Inverter makerEnphase344
SolarEdge3276
Tesla11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 320 of 326 installs, inverters on 326. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names underline energy as developer on 0 battery storage projects and as installer on 28 (0 name it as both), 28 projects in all with 437 kWh of storage. 18 have the status Paid, with $48,383 in current incentive allocations. Applications were received from Aug 1, 2021 to Dec 3, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid18255$48,383
Reserved115$1,354
Cancelled9167$48,851

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage24345$45,69916$31,337
Equity Resiliency344$44,2462$17,046
Large-Scale Storage148$8,6430$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1015714UNDERLINE ENERGY CONCEPTS (Corporation)CLEARB General Building Contractor; C-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-39 Roofing ContractorJul 1, 2016Jul 31, 2028316

License numbers are the ones the utilities recorded on the interconnection applications (326 of 326 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1015714. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list underline energy’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense201820192020202120222023202420252026Total
unincorporated San Diego County1015714121612172315311100

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
San Diego310
Orange16

Top cities

CityInstalls
San Diego93
Escondido26
Oceanside22
El Cajon21
Carlsbad15
Vista15
Spring Valley14
La Mesa13
Santee13
Lakeside10
Chula Vista9
Fallbrook9
Lemon Grove9
Alpine6
San Marcos6

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
underline energy326

Common questions

Where does underline energy install solar?

Its installs are spread across 2 counties. The most are in San Diego County (310 installs), followed by Orange County (16).

How often does underline energy install batteries with solar?

Battery storage is not recorded on its interconnected solar installs: SDG&E files a battery as its own project record, not on the solar record.

How many underline energy installs are under NEM 3.0 (the Net Billing Tariff)?

9 of its 326 interconnected installs (2.8% of the 326 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.