AWS Electrical & Solar Inc.

How many solar installs has AWS Electrical & Solar Inc. done in California, and which license number is on its installs?

AWS Electrical & Solar Inc. has 52 residential solar installs interconnected in California, active in the records from 2010 through 2019 (Sep 8, 2010 to Sep 24, 2019), most of them in Los Angeles County (26), Ventura County (11) and San Bernardino County (10). CSLB lists license 901196 (A W S ELECTRICAL SERVICES) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Jul 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
52
Last 24 months
0
Total capacity
340.6 kW DC
Median system size
6.2 kW DC
With battery storage
3.8% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 52 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
Median battery size
10 kWh (2 installs list a capacity)
First install
Sep 8, 2010
Latest install
Sep 24, 2019
Counties
5
Utilities
SCE 52
CSLB license
901196

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2010 to 2026

YearInstalls interconnectedWith battery storage
201010
201110
201200
201300
201400
201560
201682
201750
2018140
2019170
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 52 interconnected installs with a tariff recorded (52) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.02038.5%not counted
NEM 2.03261.5%0 (0.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on AWS Electrical & Solar Inc.’s installs. No residential system in the file lists a third-party owner name that matches AWS Electrical & Solar Inc. exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 50 of AWS Electrical & Solar Inc.’s 52 installs name a module maker in the “Generator Manufacturer” fields, and most of those (28, 56.0%) used modules recorded as Panasonic.

Across all years, 52 of AWS Electrical & Solar Inc.’s 52 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (41, 78.8%) used inverters recorded as SolarEdge.

Across all years, 2 of AWS Electrical & Solar Inc.’s 52 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (2, 100.0%) used batteries recorded as sonnen.

2 of 2 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerPanasonic028
SolarWorld08
Hyundai07
Canadian Solar03
LG02
Inverter makerSolarEdge041
Enphase09
SMA02
Battery makersonnen02

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 50 of 52 installs, inverters on 52. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names AWS Electrical & Solar Inc. as developer on 12 battery storage projects and as installer on 14 (12 name it as both), 14 projects in all with 339 kWh of storage. 11 have the status Paid, with $220,647 in current incentive allocations. Applications were received from Jun 17, 2020 to Dec 26, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid11260$220,647
Reserved253$52,800
Cancelled126$26,400

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency11290$289,7218$210,521
Small Residential Storage349$10,1263$10,126

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
901196A W S ELECTRICAL SERVICES (Corporation)CLEARC-10 Electrical ContractorJul 30, 2007Jul 31, 202852

License numbers are the ones the utilities recorded on the interconnection applications (52 of 52 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 901196. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
Los Angeles26
Ventura11
San Bernardino10
Orange4
Santa Barbara1

Top cities

CityInstalls
Ventura4
Apple Valley3
Canyon Country2
Lakewood2
Long Beach2
Oxnard2
Redlands2
Santa Clarita2
Santa Monica2
Simi Valley2
Yorba Linda2
Altadena1
Camarillo1
Canoga Park1
Castaic1

Names as recorded by the utilities

The utilities recorded this installer under 4 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
AWS Electrical & Solar Inc.36
AWS Electrical & Solar Inc12
AWS ELECTRICAL & SOLAR INC.3
AWS Electrical & SOlar Inc.1

Common questions

Where does AWS Electrical & Solar Inc. install solar?

Its installs are spread across 5 counties. The most are in Los Angeles County (26 installs), followed by Ventura County (11).

How often does AWS Electrical & Solar Inc. install batteries with solar?

3.8% of its interconnected solar installs include battery storage across all years.

How many AWS Electrical & Solar Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 52 interconnected installs with a tariff recorded (52) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.