Incentive Electric

How many solar installs has Incentive Electric done in California, and which license number is on its installs?

Incentive Electric has 168 residential solar installs interconnected in California, active in the records from 2021 through 2026 (Aug 26, 2021 to Aug 17, 2026), most of them in San Diego County (149), Riverside County (11) and Orange County (8). CSLB lists license 1048992 (INCENTIVE ELECTRIC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Jan 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
168
Last 24 months
57
Total capacity
1,353.5 kW DC
Median system size
7.3 kW DC
With battery storage
7.7% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 100.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
0.0% of 167 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
38 installs, latest Aug 17, 2026
Ownership types recorded
none recorded
Median battery size
13.5 kWh (1 installs list a capacity)
First install
Aug 26, 2021
Latest install
Aug 17, 2026
Counties
3
Utilities
SDGE 155, SCE 13
CSLB license
1048992

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2021 to 2026

YearInstalls interconnectedWith battery storage
202180
2022170
2023610
2024350
2025300
2026 (through Aug 31, 2026)171

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

38 of its 168 interconnected installs (22.8% of the 167 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Aug 17, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.012977.2%0 (0.0%)
Net Billing Tariff3822.8%1 (100.0%)
Not recorded1

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Incentive Electric’s installs. No residential system in the file lists a third-party owner name that matches Incentive Electric exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 49 of Incentive Electric’s 57 installs name a module maker in the “Generator Manufacturer” fields, and most of those (35, 71.4%) used modules recorded as Qcells.

In the last 24 months, 56 of Incentive Electric’s 57 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (35, 62.5%) used inverters recorded as Tesla.

In the last 24 months, 1 of Incentive Electric’s 57 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Tesla.

1 of 1 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells3582
SEGSolarInc.55
REC329
Canadian Solar2not in top list
Panasonic221
Inverter makerTesla3542
Enphase18109
SolarEdge518
ABB11
PV Powered1not in top list
Battery makerTesla11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 152 of 168 installs, inverters on 167. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Incentive Electric as developer on 0 battery storage projects and as installer on 3 (0 name it as both), 3 projects in all with 66 kWh of storage. 1 have the status Paid, with $39,600 in current incentive allocations. Applications were received from Oct 27, 2021 to Sep 20, 2022.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid140$39,600
Cancelled226$15,180

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency253$52,8001$39,600
Small Residential Storage113$1,9800$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1048992INCENTIVE ELECTRIC (Corporation)CLEARC-10 Electrical ContractorJan 15, 2019Jan 31, 2027167

License numbers are the ones the utilities recorded on the interconnection applications (167 of 168 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1048992. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Incentive Electric’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2020202120222023202420252026Total
unincorporated San Diego County104899258132037359

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
San Diego149
Riverside11
Orange8

Top cities

CityInstalls
San Diego58
Escondido12
La Mesa10
Chula Vista8
Carlsbad6
La Jolla5
Oceanside5
Poway5
Ramona5
San Marcos5
Vista5
Encinitas4
Fallbrook4
Spring Valley4
Bonita3

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Incentive Electric155
INCENTIVE ELECTRIC13

Common questions

Where does Incentive Electric install solar?

Its installs are spread across 3 counties. The most are in San Diego County (149 installs), followed by Riverside County (11).

How often does Incentive Electric install batteries with solar?

7.7% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (1 of 1). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Incentive Electric installs are under NEM 3.0 (the Net Billing Tariff)?

38 of its 168 interconnected installs (22.8% of the 167 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.