How many solar installs has Sattler Engineering done in California, and which license number is on its installs?

Sattler Engineering has 478 residential solar installs interconnected in California, active in the records from 2016 through 2026 (Oct 19, 2016 to Aug 24, 2026), most of them in San Diego County (461), Orange County (13) and Riverside County (3). CSLB lists license 1017484 (SATTLER ENGINEERING) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications A, C-10, expires Aug 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
478
Last 24 months
73
Total capacity
3,481.7 kW DC
Median system size
6.1 kW DC
With battery storage
33.3% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 100.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
0.2% of 478 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
102 installs, latest Aug 24, 2026
Ownership types recorded
prepaid lease 1
Median battery size
13.5 kWh (3 installs list a capacity)
First install
Oct 19, 2016
Latest install
Aug 24, 2026
Counties
4
Utilities
SDGE 469, SCE 9
CSLB license
1017484

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2016 to 2026

YearInstalls interconnectedWith battery storage
201620
2017170
2018170
2019330
2020270
2021621
2022880
20231260
2024430
2025472
2026 (through Aug 31, 2026)160

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

102 of its 478 interconnected installs (21.3% of the 478 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Aug 24, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.037678.7%2 (25.0%)
Net Billing Tariff10221.3%1 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 1 of Sattler Engineering’s installs the utility recorded a third-party ownership type: PPA 0, lease 0, prepaid lease 1, other 0. No residential system in the file lists a third-party owner name that matches Sattler Engineering exactly.

Third-party owner named on its installsInstalls
Sattler Solar Inc1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 72 of Sattler Engineering’s 73 installs name a module maker in the “Generator Manufacturer” fields, and most of those (44, 61.1%) used modules recorded as REC.

In the last 24 months, 73 of Sattler Engineering’s 73 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (41, 56.2%) used inverters recorded as Tesla.

In the last 24 months, 2 of Sattler Engineering’s 73 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (2, 100.0%) used batteries recorded as Tesla.

3 of 3 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerREC44165
HDHYUNDAIENERGYSOLUTIONSCO.,LTD.20not in top list
Qcells362
SEGSolarInc.2not in top list
Panasonic199
Inverter makerTesla4144
Enphase31298
Power-One1not in top list
SolarEdge1100
Battery makerTesla22

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 446 of 478 installs, inverters on 478. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Sattler Engineering as developer on 0 battery storage projects and as installer on 1 (0 name it as both), 1 projects in all with 8 kWh of storage. 1 have the status Paid, with $4,197 in current incentive allocations. Applications were received from May 1, 2017 to May 1, 2017.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid18$4,197

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage18$4,1971$4,197

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1017484SATTLER ENGINEERING (Corporation)CLEARA General Engineering Contractor; C-10 Electrical ContractorAug 23, 2016Aug 31, 2028476

License numbers are the ones the utilities recorded on the interconnection applications (478 of 478 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1017484. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Sattler Engineering’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20182019202020212022202320242025Total
unincorporated San Diego County10174841413982230

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
San Diego461
Orange13
Riverside3
Los Angeles1

Top cities

CityInstalls
San Diego312
La Jolla19
Encinitas16
Carlsbad12
La Mesa11
Escondido9
El Cajon8
Vista8
Alpine7
Chula Vista7
Solana Beach7
Oceanside6
Santee6
Del Mar5
San Marcos5

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Sattler Engineering469
SATTLER ENGINEERING9

Common questions

Where does Sattler Engineering install solar?

Its installs are spread across 4 counties. The most are in San Diego County (461 installs), followed by Orange County (13).

How often does Sattler Engineering install batteries with solar?

33.3% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (2 of 2). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Sattler Engineering installs are under NEM 3.0 (the Net Billing Tariff)?

102 of its 478 interconnected installs (21.3% of the 478 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources