SOLARE POWER LLC DBA NTW CONSTRUCTION

How many solar installs has SOLARE POWER LLC DBA NTW CONSTRUCTION done in California, and which license number is on its installs?

SOLARE POWER LLC DBA NTW CONSTRUCTION has 162 residential solar installs interconnected in California, active in the records from 2022 through 2025 (Mar 23, 2022 to Aug 25, 2025), most of them in Los Angeles County (48), Orange County (39) and Riverside County (27). The license number recorded on most of its installs, 1079237, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
162
Last 24 months
14
Total capacity
1,425.7 kW DC
Median system size
8.6 kW DC
With battery storage
6.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 28.6% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
1.2% of 162 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 2
Median battery size
10.1 kWh (9 installs list a capacity)
First install
Mar 23, 2022
Latest install
Aug 25, 2025
Counties
9
Utilities
SCE 150, SDGE 12
CSLB license
1079237

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2022 to 2026

YearInstalls interconnectedWith battery storage
2022210
2023864
2024513
202542
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 162 interconnected installs with a tariff recorded (162) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.0162100.0%9 (6.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 2 of SOLARE POWER LLC DBA NTW CONSTRUCTION’s installs the utility recorded a third-party ownership type: PPA 2, lease 0, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches SOLARE POWER LLC DBA NTW CONSTRUCTION exactly.

Third-party owner named on its installsInstalls
HDM Capital, LLC1
Sunnnova1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 13 of SOLARE POWER LLC DBA NTW CONSTRUCTION’s 14 installs name a module maker in the “Generator Manufacturer” fields, and most of those (10, 76.9%) used modules recorded as Qcells.

In the last 24 months, 14 of SOLARE POWER LLC DBA NTW CONSTRUCTION’s 14 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (8, 57.1%) used inverters recorded as Enphase.

In the last 24 months, 4 of SOLARE POWER LLC DBA NTW CONSTRUCTION’s 14 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (4, 100.0%) used batteries recorded as Enphase.

9 of 9 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells10130
SEG Solar322
Inverter makerEnphase882
SolarEdge446
APsystems (Altenergy Power System)1not in top list
SMA1not in top list
Battery makerEnphase48

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 159 of 162 installs, inverters on 162. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1079237Not found in the CSLB License Master file pulled Nov 4, 2026162

License numbers are the ones the utilities recorded on the interconnection applications (162 of 162 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Local solar permits naming its license

Solar permits in city and county open data that list SOLARE POWER LLC DBA NTW CONSTRUCTION’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2022Total
unincorporated San Diego County107923733

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Los Angeles48
Orange39
Riverside27
San Bernardino17
Ventura13
Tulare7
San Diego6
Kern3
Kings2

Top cities

CityInstalls
Corona7
Huntington Beach6
Visalia6
Fontana4
Long Beach4
Buena Park3
Chino Hills3
Diamond Bar3
Downey3
Eastvale3
Hemet3
Monterey Park3
Moreno Valley3
Murrieta3
Rancho Cucamonga3

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SOLARE POWER LLC DBA NTW CONSTRUCTION149
Solare Power LLC12
SOLARE POWER LLC1

Common questions

Where does SOLARE POWER LLC DBA NTW CONSTRUCTION install solar?

Its installs are spread across 9 counties. The most are in Los Angeles County (48 installs), followed by Orange County (39).

How often does SOLARE POWER LLC DBA NTW CONSTRUCTION install batteries with solar?

6.0% of its interconnected solar installs include battery storage across all years, and 28.6% in the last 24 months (4 of 14). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many SOLARE POWER LLC DBA NTW CONSTRUCTION installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 162 interconnected installs with a tariff recorded (162) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.