Velocity Solar

How many solar installs has Velocity Solar done in California, and which license number is on its installs?

Velocity Solar has 130 residential solar installs interconnected in California, active in the records from 2015 through 2017 (Oct 1, 2015 to Sep 26, 2017), most of them in San Joaquin County (44), Merced County (20) and Fresno County (13). CSLB lists license 1005557 (VELOCITY SOLAR POWER INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-46, expires Jul 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
130
Last 24 months
0
Total capacity
886.1 kW DC
Median system size
6.4 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
3.8% of 130 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 5
First install
Oct 1, 2015
Latest install
Sep 26, 2017
Counties
18
Utilities
PGE 130
CSLB license
1005557

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2015 to 2026

YearInstalls interconnectedWith battery storage
201540
2016340
2017920
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 130 interconnected installs with a tariff recorded (130) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.03829.2%not counted
NEM 2.09270.8%0 (0.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 5 of Velocity Solar’s installs the utility recorded a third-party ownership type: PPA 5, lease 0, prepaid lease 0, other 0. Across all installers, 1 residential systems list a third-party owner name that matches Velocity Solar exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Sunnova5

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 128 of Velocity Solar’s 130 installs name a module maker in the “Generator Manufacturer” fields, and most of those (115, 89.8%) used modules recorded as Qcells.

Across all years, 130 of Velocity Solar’s 130 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (73, 56.2%) used inverters recorded as SolarEdge.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells0115
Canadian Solar09
LG03
SolarWorld01
Inverter makerSolarEdge073
SMA051
Enphase06
Power-One01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 128 of 130 installs, inverters on 130. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1005557VELOCITY SOLAR POWER INC (Corporation)CLEARB General Building Contractor; C-46 Solar ContractorJul 14, 2015Jul 31, 2027129

License numbers are the ones the utilities recorded on the interconnection applications (130 of 130 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1005557. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Velocity Solar’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2024Total
City and County of San Francisco100555711

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
San Joaquin44
Merced20
Fresno13
Placer13
Contra Costa11
Solano6
El Dorado4
Stanislaus3
Yuba3
Butte2
Napa2
Santa Clara2
Yolo2
Alameda1
Lake1
Mariposa1
San Mateo1
Sutter1

Top cities

CityInstalls
Stockton25
Manteca16
Merced11
Fresno9
Antioch4
Clovis4
Lincoln4
Vacaville4
Atwater3
Loomis3
Los Banos3
Chico2
El Dorado Hills2
Fairfield2
Marysville2

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Velocity Solar130

Common questions

Where does Velocity Solar install solar?

Its installs are spread across 18 counties. The most are in San Joaquin County (44 installs), followed by Merced County (20).

How often does Velocity Solar install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many Velocity Solar installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 130 interconnected installs with a tariff recorded (130) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.