Safe Haven Solar
How many solar installs has Safe Haven Solar done in California, and which license number is on its installs?
Safe Haven Solar has 118 residential solar installs interconnected in California, active in the records from 2018 through 2026 (Dec 21, 2018 to Mar 23, 2026), most of them in Sutter County (30), Butte County (13) and Sonoma County (13). The license number recorded on most of its installs, 832703, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 118
- Last 24 months
- 18
- Total capacity
- 991 kW DC
- Median system size
- 8.2 kW DC
- With battery storage
- 10.2% all time; 27.8% last 24 months
- Third-party owned
- 0.0% of 118 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 14 installs, latest Mar 23, 2026
- Ownership types recorded
- none recorded
- Median battery size
- 7.3 kWh (2 installs list a capacity)
- First install
- Dec 21, 2018
- Latest install
- Mar 23, 2026
- Counties
- 21
- Utilities
- PGE 117, SCE 1
- CSLB license
- 832703, 1045220
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2018 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2018 | 2 | 0 |
| 2019 | 11 | 0 |
| 2020 | 0 | 0 |
| 2021 | 1 | 0 |
| 2022 | 0 | 0 |
| 2023 | 77 | 5 |
| 2024 | 14 | 2 |
| 2025 | 9 | 3 |
| 2026 (through Aug 31, 2026) | 4 | 2 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
14 of its 118 interconnected installs (11.9% of the 118 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 50.0% of those include battery storage. The latest Net Billing Tariff install was approved Mar 23, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 0 | 0.0% | not counted |
| NEM 2.0 | 104 | 88.1% | 5 (4.8%) |
| Net Billing Tariff | 14 | 11.9% | 7 (50.0%) |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Safe Haven Solar’s installs. No residential system in the file lists a third-party owner name that matches Safe Haven Solar exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 17 of Safe Haven Solar’s 18 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (6, 35.3%) used modules recorded as REC.
In the last 24 months, 18 of Safe Haven Solar’s 18 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (9, 50.0%) used inverters recorded as Enphase.
In the last 24 months, 5 of Safe Haven Solar’s 18 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (3, 60.0%) used batteries recorded as Tesla.
8 of 12 battery-paired PG&E and SCE installs (66.7%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | REC | 6 | 6 |
| Qcells | 3 | 23 | |
| JinkoSolar | 2 | not in top list | |
| LG | 2 | not in top list | |
| Phono Solar Technology | 2 | 12 | |
| Inverter maker | Enphase | 9 | 78 |
| Chilicon Power, LLC | 3 | 23 | |
| SolarEdge | 3 | 5 | |
| Tesla | 3 | 4 | |
| Battery maker | Tesla | 3 | 3 |
| Enphase | 2 | 4 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 109 of 118 installs, inverters on 118. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names Safe Haven Solar as developer on 0 battery storage projects and as installer on 1 (0 name it as both), 1 projects in all with 10 kWh of storage. 1 have the status Paid, with $1,303 in current incentive allocations. Applications were received from Jan 9, 2024 to Jan 9, 2024.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 1 | 10 | $1,303 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Small Residential Storage | 1 | 10 | $1,303 | 1 | $1,303 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 832703 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 103 | ||||
| 1045220 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 14 | ||||
License numbers are the ones the utilities recorded on the interconnection applications (118 of 118 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
Other names reported under the same license
- SAFE HAVEN CONST: 164 installs, license 1045220
Counties
| County | Installs |
|---|---|
| Sutter | 30 |
| Butte | 13 |
| Sonoma | 13 |
| Yuba | 13 |
| Colusa | 7 |
| Marin | 6 |
| Napa | 5 |
| Tehama | 5 |
| Solano | 4 |
| Glenn | 3 |
| Lake | 3 |
| Alameda | 2 |
| Amador | 2 |
| Contra Costa | 2 |
| Fresno | 2 |
| Placer | 2 |
| San Joaquin | 2 |
| El Dorado | 1 |
| Nevada | 1 |
| Tulare | 1 |
| Yolo | 1 |
Top cities
| City | Installs |
|---|---|
| Yuba City | 26 |
| Marysville | 7 |
| Rohnert Park | 7 |
| Colusa | 5 |
| Chico | 4 |
| Napa | 4 |
| Oroville | 4 |
| Santa Rosa | 4 |
| Berry Creek | 3 |
| Browns Valley | 3 |
| Red Bluff | 3 |
| Sutter | 3 |
| Dunlap | 2 |
| Los Molinos | 2 |
| Olivehurst | 2 |
Names as recorded by the utilities
The utilities recorded this installer under 4 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| SAFE HAVEN SOLAR | 101 |
| Safe Haven Solar | 15 |
| Safe haven Solar | 1 |
| SAFE HAVEN SOLAR DBA SAFE HAVEN CONST | 1 |
Common questions
Where does Safe Haven Solar install solar?
Its installs are spread across 21 counties. The most are in Sutter County (30 installs), followed by Butte County (13).
How often does Safe Haven Solar install batteries with solar?
10.2% of its interconnected solar installs include battery storage across all years, and 27.8% in the last 24 months (5 of 18).
How many Safe Haven Solar installs are under NEM 3.0 (the Net Billing Tariff)?
14 of its 118 interconnected installs (11.9% of the 118 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 50.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
- Self-Generation Incentive Program (SGIP) program administrators: Real-Time Public Report of SGIP applications (selfgenca.com)
Records last pulled Nov 16, 2026. Every entry links to the original public record.