How many solar installs has SOLECTRIC SOLUTION done in California, and which license number is on its installs?

SOLECTRIC SOLUTION has 181 residential solar installs interconnected in California, active in the records from 2018 through 2026 (Sep 12, 2018 to Aug 4, 2026), most of them in San Bernardino County (91), Los Angeles County (35) and Riverside County (24). CSLB lists license 1006294 (SOLECTRIC SOLUTION) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Sep 30, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
181
Last 24 months
36
Total capacity
1,858.9 kW DC
Median system size
10 kW DC
With battery storage
20.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 80.6% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
0.0% of 181 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
40 installs, latest Aug 4, 2026
Ownership types recorded
none recorded
Median battery size
13.5 kWh (35 installs list a capacity)
First install
Sep 12, 2018
Latest install
Aug 4, 2026
Counties
9
Utilities
SCE 177, PGE 3, SDGE 1
CSLB license
1006294

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2018 to 2026

YearInstalls interconnectedWith battery storage
201810
201920
202090
2021230
2022391
2023562
2024175
20253027
2026 (through Aug 31, 2026)41

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

40 of its 181 interconnected installs (22.1% of the 181 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 75.0% of those include battery storage. The latest Net Billing Tariff install was approved Aug 4, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.014177.9%6 (4.3%)
Net Billing Tariff4022.1%30 (75.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on SOLECTRIC SOLUTION’s installs. No residential system in the file lists a third-party owner name that matches SOLECTRIC SOLUTION exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 36 of SOLECTRIC SOLUTION’s 36 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (12, 33.3%) used modules recorded as Axitec.

In the last 24 months, 36 of SOLECTRIC SOLUTION’s 36 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (26, 72.2%) used inverters recorded as Tesla.

In the last 24 months, 29 of SOLECTRIC SOLUTION’s 36 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (27, 93.1%) used batteries recorded as Tesla.

36 of 36 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerAxitec1212
Aptos Solar883
SEG Solar4not in top list
Trina Solar4not in top list
Canadian Solar26
Inverter makerTesla2630
Enphase675
SolarEdge663
Battery makerTesla2727
SolarEdge23

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 175 of 181 installs, inverters on 181. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1006294SOLECTRIC SOLUTION (Corporation)CLEARC-10 Electrical ContractorAug 11, 2015Sep 30, 2027181

License numbers are the ones the utilities recorded on the interconnection applications (181 of 181 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1006294. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
San Bernardino91
Los Angeles35
Riverside24
Orange17
Ventura6
Kern3
Tulare3
San Diego1
Santa Barbara1

Top cities

CityInstalls
Rancho Cucamonga21
Victorville17
Corona16
Fontana15
Apple Valley11
Highland11
Alta Loma6
Lancaster6
Downey5
Ventura5
Glendora4
Upland4
Bakersfield3
Duarte3
Hemet3

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SOLECTRIC SOLUTION181

Common questions

Where does SOLECTRIC SOLUTION install solar?

Its installs are spread across 9 counties. The most are in San Bernardino County (91 installs), followed by Los Angeles County (35).

How often does SOLECTRIC SOLUTION install batteries with solar?

20.0% of its interconnected solar installs include battery storage across all years, and 80.6% in the last 24 months (29 of 36). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many SOLECTRIC SOLUTION installs are under NEM 3.0 (the Net Billing Tariff)?

40 of its 181 interconnected installs (22.1% of the 181 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 75.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.