SonRay Construction Inc.

How many solar installs has SonRay Construction Inc. done in California, and which license number is on its installs?

SonRay Construction Inc. has 3,909 residential solar installs interconnected in California, active in the records from 2011 through 2026 (Jul 13, 2011 to Aug 31, 2026), most of them in San Joaquin County (1,267), Placer County (851) and Yolo County (506). CSLB lists license 922628 (SONRAY CONSTRUCTION) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-20, C-39, expires Sep 30, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
3,909
Last 24 months
1,235
Total capacity
13,463.2 kW DC
Median system size
3.4 kW DC
With battery storage
11.6% all time; 31.5% last 24 months
Third-party owned
50.3% of 3,909 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
237 installs, latest Aug 31, 2026
Ownership types recorded
PPA 1,842, lease 125, prepaid lease 1
First install
Jul 13, 2011
Latest install
Aug 31, 2026
Counties
19
Utilities
PGE 3,909
CSLB license
922628

Is SonRay Construction Inc. still installing solar in California? Its latest install and its count in each month from September 2025 through August 2026 (364 in all).

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2011 to 2026

YearInstalls interconnectedWith battery storage
201110
201200
201300
201430
2015280
2016240
2017110
2018430
20191160
20202740
20216070
20227240
20233291
2024833149
2025668289
2026 (through Aug 31, 2026)24815

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

237 of its 3,909 interconnected installs (6.1% of the 3,909 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 2.1% of those include battery storage. The latest Net Billing Tariff install was approved Aug 31, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.0561.4%not counted
NEM 2.03,61692.5%449 (12.4%)
Net Billing Tariff2376.1%5 (2.1%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 1,968 of SonRay Construction Inc.’s installs the utility recorded a third-party ownership type: PPA 1,842, lease 125, prepaid lease 1, other 0. No residential system in the file lists a third-party owner name that matches SonRay Construction Inc. exactly.

Third-party owner named on its installsInstalls
Lennar1,213
Lennar Homes444
Sunnova Energy Corporation205
Century Communities35
D.R. Horton34

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 1,235 of SonRay Construction Inc.’s 1,235 installs name a module maker in the “Generator Manufacturer” fields, and most of those (737, 59.7%) used modules recorded as Qcells.

In the last 24 months, 1,235 of SonRay Construction Inc.’s 1,235 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (1,235, 100.0%) used inverters recorded as Enphase.

In the last 24 months, 389 of SonRay Construction Inc.’s 1,235 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (375, 96.4%) used batteries recorded as Tesla.

453 of 454 battery-paired PG&E and SCE installs (99.8%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells7372,478
United Renewable Energy219362
LONGi123129
Mission Solar85not in top list
Canadian Solar70not in top list
Inverter makerEnphase1,2353,795
Tesla376384
FranklinWH2not in top list
Battery makerTesla375383
Enphase1268
FranklinWH22

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 3,899 of 3,909 installs, inverters on 3,909. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
922628SONRAY CONSTRUCTION (Corporation)CLEARB General Building Contractor; C-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-39 Roofing ContractorSep 23, 2008Sep 30, 20283,393

License numbers are the ones the utilities recorded on the interconnection applications (3,404 of 3,909 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 922628. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
San Joaquin1,267
Placer851
Yolo506
Yuba495
Solano485
El Dorado191
Sutter55
Nevada29
Butte11
Amador7
Contra Costa3
Colusa2
Alameda1
Calaveras1
Fresno1
Kern1
Madera1
Sonoma1
Tehama1

Top cities

CityInstalls
Stockton760
Roseville559
Woodland401
Linda377
Tracy354
Rio Vista263
Rocklin192
El Dorado Hills157
Manteca145
Fairfield117
Plumas Lake85
West Sacramento74
Suisun City63
Lincoln59
Yuba City55

Names as recorded by the utilities

The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SONRAY CONSTRUCTION3,421
SonRay Construction Inc.406
SonRay Construction67
Sonray Construction10
SonRay Construction Inc3
SonRay Construction, Inc.2

Common questions

Where does SonRay Construction Inc. install solar?

Its installs are spread across 19 counties. The most are in San Joaquin County (1,267 installs), followed by Placer County (851).

How often does SonRay Construction Inc. install batteries with solar?

11.6% of its interconnected solar installs include battery storage across all years, and 31.5% in the last 24 months (389 of 1,235).

How many SonRay Construction Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

237 of its 3,909 interconnected installs (6.1% of the 3,909 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 2.1% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.