Verengo solar plus

How many solar installs has Verengo solar plus done in California, and which license number is on its installs?

Verengo solar plus has 646 residential solar installs interconnected in California, active in the records from 2011 through 2015 (Jun 24, 2011 to Jul 29, 2015), most of them in Los Angeles County (237), Riverside County (141) and San Bernardino County (112). The license number recorded on most of its installs, 935263, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
646
Last 24 months
0
Total capacity
3,692.2 kW DC
Median system size
5.3 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
98.9% of 261 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 258
First install
Jun 24, 2011
Latest install
Jul 29, 2015
Counties
10
Utilities
SCE 644, PGE 2
CSLB license
935263

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2011 to 2026

YearInstalls interconnectedWith battery storage
201110
201210
2013650
20143480
20152310
201600
201700
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 646 interconnected installs with a tariff recorded (646) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.0646100.0%not counted
NEM 2.000.0%0
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 258 of Verengo solar plus’s installs the utility recorded a third-party ownership type: PPA 258, lease 0, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Verengo solar plus exactly.

Third-party owner named on its installsInstalls
Sunrun, inc.210
Tredegar Solar Fund I, LLC21
Kilowatt Systems, LLC.19
Tredegar Solar Fund, LLC.4
Kilowatt System , LLC.2

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 2 of Verengo solar plus’ 646 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (1, 50.0%) used modules recorded as LG.

Across all years, 646 of Verengo solar plus’ 646 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (305, 47.2%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerLG01
Suntech01
Inverter makerEnphase0305
ABB0134
SMA0105
Power-One093
Kaco017

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 2 of 646 installs, inverters on 646. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
935263Not found in the CSLB License Master file pulled Nov 4, 2026644

License numbers are the ones the utilities recorded on the interconnection applications (644 of 646 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Other names reported under the same license

Counties

CountyInstalls
Los Angeles237
Riverside141
San Bernardino112
Orange64
Ventura38
Kern28
Tulare18
Kings6
Inyo1
Santa Barbara1

Top cities

CityInstalls
Lancaster31
Palmdale31
Corona21
Simi Valley18
Barstow16
Ridgecrest15
Blythe14
Cathedral City14
Victorville14
Riverside12
Santa Clarita11
San Bernardino10
Canyon Country9
Fontana9
Visalia9

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Verengo solar plus642
Verengo Solar Plus2
VERENGO SOLAR PLUS2

Common questions

Where does Verengo solar plus install solar?

Its installs are spread across 10 counties. The most are in Los Angeles County (237 installs), followed by Riverside County (141).

How often does Verengo solar plus install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many Verengo solar plus installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 646 interconnected installs with a tariff recorded (646) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.