PACIFIC SOLAR
How many solar installs has PACIFIC SOLAR done in California, and which license number is on its installs?
PACIFIC SOLAR has 437 residential solar installs interconnected in California, active in the records from 2004 through 2026 (Jul 7, 2004 to Aug 26, 2026), most of them in Fresno County (311), Madera County (53) and San Luis Obispo County (23). CSLB lists license 812149 (PACIFIC SOLAR) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-46, expires Aug 31, 2028.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 437
- Last 24 months
- 89
- Total capacity
- 3,802.5 kW DC
- Median system size
- 8 kW DC
- With battery storage
- 20.6% all time; 76.4% last 24 months
- Third-party owned
- 4.6% of 436 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 101 installs, latest Aug 26, 2026
- Ownership types recorded
- PPA 5, lease 15
- Median battery size
- 15 kWh (37 installs list a capacity)
- First install
- Jul 7, 2004
- Latest install
- Aug 26, 2026
- Counties
- 15
- Utilities
- PGE 417, SCE 20
- CSLB license
- 812149
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2004 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2004 | 1 | 0 |
| 2005 | 1 | 0 |
| 2006 | 0 | 0 |
| 2007 | 3 | 0 |
| 2008 | 2 | 0 |
| 2009 | 4 | 0 |
| 2010 | 5 | 0 |
| 2011 | 4 | 0 |
| 2012 | 3 | 0 |
| 2013 | 0 | 0 |
| 2014 | 4 | 0 |
| 2015 | 1 | 0 |
| 2016 | 0 | 0 |
| 2017 | 0 | 0 |
| 2018 | 0 | 0 |
| 2019 | 23 | 1 |
| 2020 | 65 | 1 |
| 2021 | 68 | 3 |
| 2022 | 62 | 1 |
| 2023 | 73 | 4 |
| 2024 | 41 | 17 |
| 2025 | 50 | 39 |
| 2026 (through Aug 31, 2026) | 27 | 24 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
101 of its 437 interconnected installs (23.1% of the 437 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 80.2% of those include battery storage. The latest Net Billing Tariff install was approved Aug 26, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 28 | 6.4% | not counted |
| NEM 2.0 | 308 | 70.5% | 9 (2.9%) |
| Net Billing Tariff | 101 | 23.1% | 81 (80.2%) |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
On 20 of PACIFIC SOLAR’s installs the utility recorded a third-party ownership type: PPA 5, lease 15, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches PACIFIC SOLAR exactly.
| Third-party owner named on its installs | Installs |
|---|---|
| SunPower Capital, LLC | 14 |
| Lightreach | 4 |
| Goodleap | 2 |
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 86 of PACIFIC SOLAR’s 89 installs name a module maker in the “Generator Manufacturer” fields, and most of those (52, 60.5%) used modules recorded as SunPower.
In the last 24 months, 89 of PACIFIC SOLAR’s 89 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (45, 50.6%) used inverters recorded as Enphase.
In the last 24 months, 53 of PACIFIC SOLAR’s 89 installs name a battery maker in the “Generator Manufacturer” fields, and the most common maker (22, 41.5%) used batteries recorded as FranklinWH.
68 of 90 battery-paired PG&E and SCE installs (75.6%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | SunPower | 52 | 340 |
| Solaria | 12 | 13 | |
| LONGi | 6 | 6 | |
| Qcells | 4 | not in top list | |
| Trina Solar | 4 | not in top list | |
| Inverter maker | Enphase | 45 | 70 |
| Tesla | 33 | 34 | |
| FranklinWH | 20 | 21 | |
| SunPower | 7 | 311 | |
| Fronius | 2 | not in top list | |
| Battery maker | FranklinWH | 22 | 23 |
| Tesla | 21 | 21 | |
| Enphase | 8 | 11 | |
| Sigenergy | 1 | not in top list | |
| SunPower | 1 | 11 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 399 of 437 installs, inverters on 437. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 812149 | PACIFIC SOLAR (Corporation) | CLEAR | B General Building Contractor; C-10 Electrical Contractor; C-46 Solar Contractor | Aug 30, 2002 | Aug 31, 2028 | 409 |
License numbers are the ones the utilities recorded on the interconnection applications (409 of 437 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 812149. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Other names reported under the same license
- Valley Pacific Builders, Inc. dba Pacifi: 415 installs, license 812149
Counties
| County | Installs |
|---|---|
| Fresno | 311 |
| Madera | 53 |
| San Luis Obispo | 23 |
| Tulare | 20 |
| Kings | 8 |
| Merced | 5 |
| Kern | 4 |
| Marin | 3 |
| Placer | 2 |
| San Francisco | 2 |
| Tuolumne | 2 |
| Alameda | 1 |
| Amador | 1 |
| El Dorado | 1 |
| Monterey | 1 |
Top cities
| City | Installs |
|---|---|
| Fresno | 163 |
| Clovis | 89 |
| Madera | 33 |
| Sanger | 15 |
| Reedley | 12 |
| Coarsegold | 9 |
| Kingsburg | 9 |
| Visalia | 7 |
| Arroyo Grande | 5 |
| Lemoore | 5 |
| Atascadero | 4 |
| Bakersfield | 4 |
| Caruthers | 4 |
| Chowchilla | 4 |
| Porterville | 4 |
Names as recorded by the utilities
The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| PACIFIC SOLAR | 410 |
| Pacific Solar | 21 |
| Pacific Solar Company, Inc. | 3 |
| Pacific Solar Company | 2 |
| Pacific Solar Co Inc | 1 |
Common questions
Where does PACIFIC SOLAR install solar?
Its installs are spread across 15 counties. The most are in Fresno County (311 installs), followed by Madera County (53).
How often does PACIFIC SOLAR install batteries with solar?
20.6% of its interconnected solar installs include battery storage across all years, and 76.4% in the last 24 months (68 of 89).
How many PACIFIC SOLAR installs are under NEM 3.0 (the Net Billing Tariff)?
101 of its 437 interconnected installs (23.1% of the 437 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 80.2% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.