AMS Solar Power
How many solar installs has AMS Solar Power done in California, and which license number is on its installs?
AMS Solar Power has 47 residential solar installs interconnected in California, active in the records from 2022 through 2026 (Oct 14, 2022 to Jun 25, 2026), most of them in San Diego County (27), San Bernardino County (7) and Orange County (4). The license number recorded on most of its installs, 1095303, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 47
- Last 24 months
- 8
- Total capacity
- 378.5 kW DC
- Median system size
- 7.6 kW DC
- With battery storage
- 27.8% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 100.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
- Third-party owned
- 0.0% of 47 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 5 installs, latest Jun 25, 2026
- Ownership types recorded
- none recorded
- Median battery size
- 27 kWh (5 installs list a capacity)
- First install
- Oct 14, 2022
- Latest install
- Jun 25, 2026
- Counties
- 7
- Utilities
- SDGE 29, SCE 18
- CSLB license
- 1095303
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2022 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2022 | 11 | 1 |
| 2023 | 24 | 0 |
| 2024 | 5 | 0 |
| 2025 | 3 | 2 |
| 2026 (through Aug 31, 2026) | 4 | 2 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
5 of its 47 interconnected installs (10.6% of the 47 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Jun 25, 2026.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 0 | 0.0% | not counted |
| NEM 2.0 | 42 | 89.4% | 2 (13.3%) |
| Net Billing Tariff | 5 | 10.6% | 3 (100.0%) |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on AMS Solar Power’s installs. No residential system in the file lists a third-party owner name that matches AMS Solar Power exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 8 of AMS Solar Power’s 8 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (2, 25.0%) used modules recorded as Qcells.
In the last 24 months, 8 of AMS Solar Power’s 8 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (3, 37.5%) used inverters recorded as SolarEdge.
In the last 24 months, 4 of AMS Solar Power’s 8 installs name a battery maker in the “Generator Manufacturer” fields, and the most common maker (2, 50.0%) used batteries recorded as FranklinWH.
4 of 5 battery-paired PG&E and SCE installs (80.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Qcells | 2 | 20 |
| Bluesun | 1 | 1 | |
| JinkoSolar | 1 | not in top list | |
| LONGi | 1 | not in top list | |
| Mitrex | 1 | 13 | |
| Inverter maker | SolarEdge | 3 | 9 |
| Enphase | 2 | 32 | |
| EG4 | 1 | not in top list | |
| Sol-Ark | 1 | not in top list | |
| Tesla | 1 | 2 | |
| Battery maker | FranklinWH | 2 | 2 |
| EG4 | 1 | 1 | |
| Tesla | 1 | 1 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 44 of 47 installs, inverters on 47. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names AMS Solar Power as developer on 4 battery storage projects and as installer on 4 (4 name it as both), 4 projects in all with 93 kWh of storage. 1 have the status Paid, with $29,995 in current incentive allocations. Applications were received from Jan 20, 2023 to Dec 18, 2025.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 1 | 30 | $29,995 |
| Reserved | 2 | 53 | $49,780 |
| Cancelled | 1 | 10 | $1,456 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Equity Resiliency | 3 | 83 | $79,775 | 1 | $29,995 |
| Small Residential Storage | 1 | 10 | $1,456 | 0 | $0 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 1095303 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 47 | ||||
License numbers are the ones the utilities recorded on the interconnection applications (47 of 47 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
Local solar permits naming its license
Solar permits in city and county open data that list AMS Solar Power’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2022 | 2023 | Total |
|---|---|---|---|---|
| unincorporated San Diego County | 1095303 | 1 | 7 | 8 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Other names reported under the same license
- AMS BUILDERS: 96 installs, license 1095303
Counties
| County | Installs |
|---|---|
| San Diego | 27 |
| San Bernardino | 7 |
| Orange | 4 |
| Riverside | 4 |
| Los Angeles | 2 |
| Ventura | 2 |
| Kern | 1 |
Top cities
| City | Installs |
|---|---|
| San Diego | 10 |
| Chula Vista | 4 |
| El Cajon | 4 |
| Carlsbad | 3 |
| Escondido | 3 |
| Corona | 2 |
| Highland | 2 |
| Oceanside | 2 |
| San Bernardino | 2 |
| San Clemente | 2 |
| Simi Valley | 2 |
| Alta Loma | 1 |
| Del Mar | 1 |
| Fontana | 1 |
| Fullerton | 1 |
Names as recorded by the utilities
The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| AMS Solar Power | 29 |
| AMS SOLAR POWER INC DBA AMS BUILDERS | 10 |
| AMS SOLAR POWER INC | 8 |
Common questions
Where does AMS Solar Power install solar?
Its installs are spread across 7 counties. The most are in San Diego County (27 installs), followed by San Bernardino County (7).
How often does AMS Solar Power install batteries with solar?
27.8% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (4 of 4). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many AMS Solar Power installs are under NEM 3.0 (the Net Billing Tariff)?
5 of its 47 interconnected installs (10.6% of the 47 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
- Self-Generation Incentive Program (SGIP) program administrators: Real-Time Public Report of SGIP applications (selfgenca.com)
Records last pulled Nov 16, 2026. Every entry links to the original public record.