NRG Home Solar

How many solar installs has NRG Home Solar done in California, and which license number is on its installs?

NRG Home Solar has 363 residential solar installs interconnected in California, active in the records from 2014 through 2016 (Sep 30, 2014 to Nov 8, 2016), most of them in San Diego County (81), Los Angeles County (34) and Fresno County (31). The license number recorded on most of its installs, 999550, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
363
Last 24 months
0
Total capacity
1,907 kW DC
Median system size
4.9 kW DC
With battery storage
0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
64.9% of 328 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 4, lease 207, prepaid lease 2
First install
Sep 30, 2014
Latest install
Nov 8, 2016
Counties
32
Utilities
PGE 187, SDGE 90, SCE 86
CSLB license
999550

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2014 to 2026

YearInstalls interconnectedWith battery storage
201460
20152060
20161510
201700
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 363 interconnected installs with a tariff recorded (363) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.036099.2%not counted
NEM 2.030.8%not recorded
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 213 of NRG Home Solar’s installs the utility recorded a third-party ownership type: PPA 4, lease 207, prepaid lease 2, other 0. Across all installers, 207 residential systems list a third-party owner name that matches NRG Home Solar exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
NRG Home Solar204
ngr home solar5
NRG2
NRG H1
Shelley Snyder1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 362 of NRG Home Solar’s 363 installs name a module maker in the “Generator Manufacturer” fields, and most of those (215, 59.4%) used modules recorded as LG.

Across all years, 363 of NRG Home Solar’s 363 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (331, 91.2%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerLG0215
Canadian Solar074
Trina Solar071
Lumos01
SolarWorld01
Inverter makerEnphase0331
SolarEdge024
SMA06
Power-One02

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 362 of 363 installs, inverters on 363. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
999550Not found in the CSLB License Master file pulled Nov 4, 2026275

License numbers are the ones the utilities recorded on the interconnection applications (276 of 363 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Counties

CountyInstalls
San Diego81
Los Angeles34
Fresno31
San Joaquin28
Orange23
Merced19
Santa Clara18
Tulare18
Stanislaus17
Alameda14
San Bernardino12
Contra Costa11
Riverside9
Solano5
Tuolumne5
El Dorado4
Madera4
Placer4
Kern3
Monterey3
Ventura3
Kings2
Marin2
San Luis Obispo2
San Mateo2
Sutter2
Yuba2
Calaveras1
Lake1
Santa Barbara1
Sonoma1
Yolo1

Top cities

CityInstalls
San Diego33
Stockton18
Fresno14
San Jose11
El Cajon10
Newman9
Oceanside9
Atwater8
Sanger7
Visalia6
Chula Vista5
Kerman5
Merced5
Porterville5
Riverbank5

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
NRG Home Solar213
nrg home solar111
NRG HOME SOLAR39

Common questions

Where does NRG Home Solar install solar?

Its installs are spread across 32 counties. The most are in San Diego County (81 installs), followed by Los Angeles County (34).

How often does NRG Home Solar install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many NRG Home Solar installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 363 interconnected installs with a tariff recorded (363) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.