ORIGIN SOLAR USA INC

How many solar installs has ORIGIN SOLAR USA INC done in California, and which license number is on its installs?

ORIGIN SOLAR USA INC has 208 residential solar installs interconnected in California, active in the records from 2023 through 2026 (Jan 23, 2023 to Aug 28, 2026), most of them in San Joaquin County (29), Alameda County (19) and Solano County (18). CSLB lists license 1094790 (NORTH VALLEY CAPITAL) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-20, C-39, expires Jul 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
208
Last 24 months
171
Total capacity
1,808.3 kW DC
Median system size
7.5 kW DC
With battery storage
82.7% all time; 98.2% last 24 months
Third-party owned
57.7% of 208 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
171 installs, latest Aug 28, 2026
Ownership types recorded
PPA 119, lease 1
Median battery size
13.5 kWh (17 installs list a capacity)
First install
Jan 23, 2023
Latest install
Aug 28, 2026
Counties
33
Utilities
PGE 207, SCE 1
CSLB license
1094790

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2023 to 2026

YearInstalls interconnectedWith battery storage
2023322
2024128
20258686
2026 (through Aug 31, 2026)7876

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

171 of its 208 interconnected installs (82.2% of the 208 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 98.2% of those include battery storage. The latest Net Billing Tariff install was approved Aug 28, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.021.0%not counted
NEM 2.03516.8%3 (8.6%)
Net Billing Tariff17182.2%168 (98.2%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 120 of ORIGIN SOLAR USA INC’s installs the utility recorded a third-party ownership type: PPA 119, lease 1, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches ORIGIN SOLAR USA INC exactly.

Third-party owner named on its installsInstalls
Solwerks47
Goodleap44
Solwerks Power Inc.15
Everbright4
Wheelhouse4

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 170 of ORIGIN SOLAR USA INC’s 171 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (51, 30.0%) used modules recorded as LONGi.

In the last 24 months, 171 of ORIGIN SOLAR USA INC’s 171 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (125, 73.1%) used inverters recorded as Enphase.

In the last 24 months, 161 of ORIGIN SOLAR USA INC’s 171 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (116, 72.0%) used batteries recorded as Enphase.

164 of 172 battery-paired PG&E and SCE installs (95.3%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerLONGi5152
Qcells4949
JA Solar4041
Znshine820
REC7not in top list
Inverter makerEnphase125157
Tesla4849
SolarEdge816
SMA34
ABB23
Battery makerEnphase116118
Tesla4344
FranklinWH11
LG11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 199 of 208 installs, inverters on 208. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names ORIGIN SOLAR USA INC as developer on 3 battery storage projects and as installer on 1 (1 name it as both), 3 projects in all with 40 kWh of storage. 1 have the status Paid, with $13,200 in current incentive allocations. Applications were received from May 28, 2025 to May 7, 2026.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid113$13,200
Reserved113$29,180
Pending Reservation113$10,500

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Residential Solar and Storage Equity - AB 209 Non-POU226$39,6800$0
Equity Resiliency113$13,2001$13,200

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1094790NORTH VALLEY CAPITAL (Corporation)CLEAR, Pending Case/CITB General Building Contractor; C-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-39 Roofing ContractorJul 29, 2022Jul 31, 2028208

License numbers are the ones the utilities recorded on the interconnection applications (208 of 208 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1094790. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list ORIGIN SOLAR USA INC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20252026Total
City and County of San Francisco1094790202
unincorporated San Diego County1094790011

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
San Joaquin29
Alameda19
Solano18
Contra Costa15
El Dorado15
Humboldt15
Placer14
Yolo11
Tehama10
Sutter7
Shasta6
Sonoma6
Nevada5
Butte4
Yuba4
Glenn3
Lake3
Mendocino3
Santa Cruz3
Amador2
Fresno2
San Benito2
Santa Clara2
Los Angeles1
Madera1
Marin1
Merced1
Monterey1
Napa1
San Francisco1
San Mateo1
Stanislaus1
Trinity1

Top cities

CityInstalls
Stockton19
Oakland10
Eureka8
El Dorado Hills6
Woodland6
Corning5
Lincoln5
Tracy5
Vacaville5
Fairfield4
Grass Valley4
Hayward4
Placerville4
Anderson3
Dixon3

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
ORIGIN SOLAR USA INC208

Common questions

Where does ORIGIN SOLAR USA INC install solar?

Its installs are spread across 33 counties. The most are in San Joaquin County (29 installs), followed by Alameda County (19).

How often does ORIGIN SOLAR USA INC install batteries with solar?

82.7% of its interconnected solar installs include battery storage across all years, and 98.2% in the last 24 months (168 of 171).

How many ORIGIN SOLAR USA INC installs are under NEM 3.0 (the Net Billing Tariff)?

171 of its 208 interconnected installs (82.2% of the 208 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 98.2% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.