How many solar installs has THOR ELECTRIC SERVICES INC done in California, and which license number is on its installs?

THOR ELECTRIC SERVICES INC has 158 residential solar installs interconnected in California, active in the records from 2019 through 2024 (Jul 29, 2019 to Jul 3, 2024), most of them in Contra Costa County (22), San Joaquin County (18) and El Dorado County (15). The license number recorded on most of its installs, 1042900, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
158
Last 24 months
0
Total capacity
1,277.3 kW DC
Median system size
7.6 kW DC
With battery storage
12.0% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 158 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
Median battery size
9.3 kWh (12 installs list a capacity)
First install
Jul 29, 2019
Latest install
Jul 3, 2024
Counties
28
Utilities
PGE 158
CSLB license
1042900

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2019 to 2026

YearInstalls interconnectedWith battery storage
201910
2020440
2021777
2022268
202393
202411
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 158 interconnected installs with a tariff recorded (158) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.0158100.0%19 (12.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on THOR ELECTRIC SERVICES INC’s installs. No residential system in the file lists a third-party owner name that matches THOR ELECTRIC SERVICES INC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 148 of THOR ELECTRIC SERVICES INC’s 158 installs name a module maker in the “Generator Manufacturer” fields, and most of those (83, 56.1%) used modules recorded as Qcells.

Across all years, 158 of THOR ELECTRIC SERVICES INC’s 158 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (77, 48.7%) used inverters recorded as Enphase.

Across all years, 17 of THOR ELECTRIC SERVICES INC’s 158 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (9, 52.9%) used batteries recorded as LG.

17 of 19 battery-paired PG&E and SCE installs (89.5%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells083
LG029
SunPower09
JinkoSolar06
REC06
Inverter makerEnphase077
SolarEdge064
SunPower09
SMA07
Generac06
Battery makerLG09
Generac05
Enphase03

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 148 of 158 installs, inverters on 158. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names THOR ELECTRIC SERVICES INC as developer on 3 battery storage projects and as installer on 2 (2 name it as both), 3 projects in all with 68 kWh of storage. 2 have the status Paid, with $34,359 in current incentive allocations. Applications were received from Apr 3, 2022 to Feb 12, 2024.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid258$34,359
Cancelled110$1,456

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency129$29,1181$29,118
Large-Scale Storage129$5,2411$5,241
Small Residential Storage110$1,4560$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1042900Not found in the CSLB License Master file pulled Nov 4, 2026157

License numbers are the ones the utilities recorded on the interconnection applications (158 of 158 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Local solar permits naming its license

Solar permits in city and county open data that list THOR ELECTRIC SERVICES INC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20192021Total
City and County of San Francisco1042900022
unincorporated Marin County1042900112

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
Contra Costa22
San Joaquin18
El Dorado15
Alameda14
Santa Clara14
Napa12
Placer9
Yolo8
Marin7
Sonoma6
Fresno5
San Mateo4
Sutter4
Amador2
San Benito2
Shasta2
Stanislaus2
Yuba2
Butte1
Madera1
Mariposa1
Mendocino1
Monterey1
Nevada1
San Francisco1
Solano1
Tehama1
Tulare1

Top cities

CityInstalls
Napa11
Stockton9
Tracy7
Lincoln5
San Jose5
West Sacramento5
Antioch4
Hayward4
Placerville4
Concord3
Martinez3
Oakland3
Sonoma3
Yuba City3
Cool2

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
THOR ELECTRIC SERVICES INC155
Thor Electric Services, Inc.2
Thor Electric Services Inc.1

Common questions

Where does THOR ELECTRIC SERVICES INC install solar?

Its installs are spread across 28 counties. The most are in Contra Costa County (22 installs), followed by San Joaquin County (18).

How often does THOR ELECTRIC SERVICES INC install batteries with solar?

12.0% of its interconnected solar installs include battery storage across all years.

How many THOR ELECTRIC SERVICES INC installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 158 interconnected installs with a tariff recorded (158) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.