Solar City
How many solar installs has Solar City done in California, and which license number is on its installs?
Solar City has 697 residential solar installs interconnected in California, active in the records from 2006 through 2019 (Nov 20, 2006 to May 22, 2019), most of them in Santa Clara County (195), Fresno County (95) and San Mateo County (91). CSLB lists license 888104 (TESLA ENERGY OPERATIONS INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-39, C-46, expires Dec 31, 2026.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 697
- Last 24 months
- 0
- Total capacity
- 3,387.1 kW DC
- Median system size
- 4 kW DC
- With battery storage
- 0.7% all time; no installs in the last 24 months last 24 months
- Third-party owned
- 6.8% of 695 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- PPA 21, lease 21, other 5
- First install
- Nov 20, 2006
- Latest install
- May 22, 2019
- Counties
- 35
- Utilities
- PGE 687, SCE 10
- CSLB license
- 888104
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2006 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2006 | 1 | 0 |
| 2007 | 163 | 0 |
| 2008 | 178 | 0 |
| 2009 | 177 | 0 |
| 2010 | 26 | 0 |
| 2011 | 23 | 0 |
| 2012 | 15 | 0 |
| 2013 | 42 | 0 |
| 2014 | 8 | 0 |
| 2015 | 5 | 0 |
| 2016 | 0 | 0 |
| 2017 | 50 | 1 |
| 2018 | 8 | 3 |
| 2019 | 1 | 1 |
| 2020 | 0 | 0 |
| 2021 | 0 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 697 interconnected installs with a tariff recorded (697) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 638 | 91.5% | not counted |
| NEM 2.0 | 59 | 8.5% | 5 (8.5%) |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
On 47 of Solar City’s installs the utility recorded a third-party ownership type: PPA 21, lease 21, prepaid lease 0, other 5. Across all installers, 1,191 residential systems list a third-party owner name that matches Solar City exactly (after removing case, punctuation and suffixes such as Inc or LLC).
| Third-party owner named on its installs | Installs |
|---|---|
| Solar City | 29 |
| SolarCity | 8 |
| Tomorrow Comes Today, LLC | 2 |
| USB SolarCity Owner IV, LLC | 2 |
| AU Solar 1, LLC | 1 |
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 676 of Solar City’s 697 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (167, 24.7%) used modules recorded as BP Solar.
Across all years, 696 of Solar City’s 697 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (327, 47.0%) used inverters recorded as Xantrex Technology Inc..
Across all years, 5 of Solar City’s 697 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (5, 100.0%) used batteries recorded as Tesla.
5 of 5 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | BP Solar | 0 | 167 |
| Kyocera | 0 | 133 | |
| Evergreen Solar | 0 | 131 | |
| Sanyo | 0 | 55 | |
| First Solar | 0 | 47 | |
| Inverter maker | Xantrex Technology Inc. | 0 | 327 |
| Fronius | 0 | 242 | |
| Power-One | 0 | 47 | |
| ABB | 0 | 29 | |
| SolarEdge | 0 | 24 | |
| Battery maker | Tesla | 0 | 5 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 676 of 697 installs, inverters on 696. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names Solar City as developer on 0 battery storage projects and as installer on 57 (0 name it as both), 57 projects in all with 698 kWh of storage. 54 have the status Paid, with $569,040 in current incentive allocations. Applications were received from Nov 22, 2011 to Feb 5, 2018.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 54 | 648 | $569,040 |
| Cancelled | 3 | 50 | $32,560 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Small Residential Storage | 11 | 238 | $90,160 | 9 | $69,600 |
| Not stated | 46 | 460 | $511,440 | 45 | $499,440 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 888104 | TESLA ENERGY OPERATIONS INC (Corporation) | CLEAR, Class Removal Pending | B General Building Contractor; C-10 Electrical Contractor; C-39 Roofing Contractor; C-46 Solar Contractor | Dec 7, 2006 | Dec 31, 2026 | 55 |
License numbers are the ones the utilities recorded on the interconnection applications (63 of 697 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The License Master file lists a pending classification removal date of Dec 30, 2026 for license 888104. A pending date is CSLB’s scheduled action if the underlying requirement is not met; it is not a finding of wrongdoing.
What a disciplinary bond is: CSLB’s Bond Basics page says that when a license has been revoked, or in some instances suspended, for a violation of the Contractors State License Law, the contractor must file a disciplinary bond with the Registrar to reinstate, reissue or reapply for a license, and that the bond must stay on file for at least two years (CSLB Bond Basics). The file gives one disciplinary bond entry per license and does not say which of those circumstances applied, what the case was about or how it ended. CSLB’s license detail page shows any public disciplinary action.
Local solar permits naming its license
Solar permits in city and county open data that list Solar City’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|
| City and County of San Francisco | 888104 | 126 | 92 | 134 | 102 | 79 | 60 | 40 | 35 | 24 | 692 |
| unincorporated San Diego County | 888104 | 369 | 322 | 409 | 425 | 267 | 203 | 69 | 82 | 52 | 2,198 |
| unincorporated Marin County | 888104 | 61 | 77 | 159 | 110 | 0 | 0 | 2 | 2 | 1 | 412 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Other names reported under the same license
- Tesla Energy Operations (formerly SolarCity): 216,521 installs, license 888104
- Tesla: 591 installs, license 888104
- SolarCity Corporation - Tiffany: 370 installs, license 888104
- Tesla Energy Ops, Inc.: 204 installs, license 888104
- SolarCity Corporation - Amanda Tsai: 195 installs, license 888104
- SolarCity Corporation - Julia: 177 installs, license 888104
- So Cal Custom Inc.: 87 installs, license 888104
- Tesla Energy Operation, Inc: 59 installs, license 888104
Counties
Top cities
| City | Installs |
|---|---|
| Mountain View | 73 |
| San Francisco | 61 |
| Fresno | 53 |
| San Jose | 53 |
| Clovis | 35 |
| Bakersfield | 31 |
| Menlo Park | 19 |
| Oakland | 18 |
| Woodside | 15 |
| Los Altos | 14 |
| Berkeley | 13 |
| Stanford | 13 |
| San Carlos | 11 |
| Fremont | 10 |
| Atherton | 9 |
Names as recorded by the utilities
The utilities recorded this installer under 10 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Solar City | 601 |
| Solar City Corporation | 65 |
| SOLAR CITY | 11 |
| Solar City Corp | 11 |
| Solar City DBA Tesla | 3 |
| SOLAR CITY CORPORATION | 2 |
| solar city | 1 |
| Solar city | 1 |
| Solar CIty | 1 |
| Solar CIty DBA Tesla | 1 |
Common questions
Where does Solar City install solar?
Its installs are spread across 35 counties. The most are in Santa Clara County (195 installs), followed by Fresno County (95).
How often does Solar City install batteries with solar?
0.7% of its interconnected solar installs include battery storage across all years.
How many Solar City installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 697 interconnected installs with a tariff recorded (697) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056