How many solar installs has Tesla Energy Ops, Inc. done in California, and which license number is on its installs?

Tesla Energy Ops, Inc. has 204 residential solar installs interconnected in California, active in the records from 2018 through 2019 (Feb 20, 2018 to Aug 7, 2019), most of them in Contra Costa County (28), Alameda County (24) and Santa Clara County (23). CSLB lists license 888104 (TESLA ENERGY OPERATIONS INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-39, C-46, expires Dec 31, 2026.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

The installs credited to Tesla Energy Ops, Inc. here carry more than one CSLB license number: 888104 on 190 (CSLB holder TESLA ENERGY OPERATIONS INC, Fremont) and 888401 on 13 (CSLB holder Sole owner license (name not shown)), in the License Master file pulled Nov 4, 2026. They are grouped under one installer by the name written on the applications; the records do not say whether these numbers belong to the same legal entity.

Interconnected installs
204
Last 24 months
0
Total capacity
1,176.5 kW DC
Median system size
5 kW DC
With battery storage
3.9% all time; no installs in the last 24 months last 24 months
Third-party owned
25.0% of 204 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 20, lease 30, other 1
Median battery size
27 kWh (1 installs list a capacity)
First install
Feb 20, 2018
Latest install
Aug 7, 2019
Counties
32
Utilities
PGE 202, SCE 2
CSLB license
888104, 888401

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2018 to 2026

YearInstalls interconnectedWith battery storage
20182037
201911
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 204 interconnected installs with a tariff recorded (204) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.010.5%not counted
NEM 2.020399.5%7 (3.4%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 51 of Tesla Energy Ops, Inc.’s installs the utility recorded a third-party ownership type: PPA 20, lease 30, prepaid lease 0, other 1. Across all installers, 189 residential systems list a third-party owner name that matches Tesla Energy Ops, Inc. exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Tesla Energy Ops28
SolarCity22
Solar City1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 199 of Tesla Energy Ops, Inc.’s 204 installs name a module maker in the “Generator Manufacturer” fields, and most of those (117, 58.8%) used modules recorded as SolarCity.

Across all years, 204 of Tesla Energy Ops, Inc.’s 204 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (102, 50.0%) used inverters recorded as Delta Electronics.

Across all years, 4 of Tesla Energy Ops, Inc.’s 204 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (4, 100.0%) used batteries recorded as Tesla.

4 of 8 battery-paired PG&E and SCE installs (50.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSolarCity0117
Trina Solar074
LG03
Kyocera02
Canadian Solar01
Inverter makerDelta Electronics0102
SolarEdge056
ABB046
Tesla07
SolarCity04
Battery makerTesla04

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 199 of 204 installs, inverters on 204. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Tesla Energy Ops, Inc. as developer on 0 battery storage projects and as installer on 1 (0 name it as both), 1 projects in all with 26 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from May 14, 2018 to May 14, 2018.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Cancelled126$8,120

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage126$8,1200$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
888104TESLA ENERGY OPERATIONS INC (Corporation)CLEAR, Class Removal PendingB General Building Contractor; C-10 Electrical Contractor; C-39 Roofing Contractor; C-46 Solar ContractorDec 7, 2006Dec 31, 2026190
888401Sole owner license (name not shown)CLEARC-10 Electrical ContractorDec 14, 2006Dec 31, 202613

License numbers are the ones the utilities recorded on the interconnection applications (204 of 204 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The License Master file lists a pending classification removal date of Dec 30, 2026 for license 888104. A pending date is CSLB’s scheduled action if the underlying requirement is not met; it is not a finding of wrongdoing.

What a disciplinary bond is: CSLB’s Bond Basics page says that when a license has been revoked, or in some instances suspended, for a violation of the Contractors State License Law, the contractor must file a disciplinary bond with the Registrar to reinstate, reissue or reapply for a license, and that the bond must stay on file for at least two years (CSLB Bond Basics). The file gives one disciplinary bond entry per license and does not say which of those circumstances applied, what the case was about or how it ended. CSLB’s license detail page shows any public disciplinary action.

Local solar permits naming its license

Solar permits in city and county open data that list Tesla Energy Ops, Inc.’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense201820192020202120222023202420252026Total
City and County of San Francisco888104126921341027960403524692
unincorporated San Diego County8881043693224094252672036982522,198
unincorporated Marin County888104617715911000221412

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Contra Costa28
Alameda24
Santa Clara23
San Joaquin22
Fresno17
Sonoma15
Kern11
Solano8
San Mateo7
Placer6
Madera5
San Luis Obispo5
Marin4
Monterey4
San Francisco4
Butte2
El Dorado2
Santa Barbara2
Yolo2
Calaveras1
Kings1
Lake1
Los Angeles1
Mariposa1
Merced1
Orange1
San Benito1
Santa Cruz1
Shasta1
Stanislaus1
Sutter1
Tulare1

Top cities

CityInstalls
San Jose13
Bakersfield11
Fresno11
Stockton9
San Ramon8
Dublin7
Santa Rosa7
Antioch4
Clovis4
Gilroy4
Lathrop4
Livermore4
Manteca4
Oakley4
San Francisco4

Names as recorded by the utilities

The utilities recorded this installer under 8 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Tesla Energy Ops, Inc.119
Tesla Energy Ops37
Tesla Energy Ops, Inc31
tesla energy ops13
Tesla energy ops1
Tesla Energy ops1
TESLA ENERGY OPS1
Tesla Energy ops, Inc1

Common questions

Where does Tesla Energy Ops, Inc. install solar?

Its installs are spread across 32 counties. The most are in Contra Costa County (28 installs), followed by Alameda County (24).

How often does Tesla Energy Ops, Inc. install batteries with solar?

3.9% of its interconnected solar installs include battery storage across all years.

How many Tesla Energy Ops, Inc. installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 204 interconnected installs with a tariff recorded (204) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.